170 |

TAR NC Implementation Document – Second Edition September 2017

CALENDAR YEAR 2020

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Figure 49:

General timeline for 2020

(BG, CZ, DE, ES, FI, GR, HR, IT, LT,

LU, NL, PL, SI, SK)

Art. 30:

Publication of tariff information

before tariff period

(‘NEW tariffs’)

Dec 2020

(DK, HU, IE, NIR, RO, SE, GB)

Art. 30:

Publication of tariff information

before tariff period

(‘NEW tariffs’)

Sep 2020

(FR)

Art. 30:

Publication of tariff

information before tariff

period

(‘NEW tariffs’)

Mar 2020

(ENTSOG)

Art. 36(1)(a): Deadline to

send information to ACER on

compliance with Chapters other

than Chapter VIII

31 Mar 2020

\\

Jan–Dec tariff period:

‘NEW’ tariffs (Oct ’20–Dec ’20),

‘NEW’ tariffs (Jan ’21–Sep ’21)

\\

Apr–Mar tariff period:

‘NEW’ tariffs (Oct ’20–Mar ’21),

‘NEW’ tariffs (Apr ’21–Sep ’21)

\\

Jul–Jun tariff period:

‘NEW’ tariffs (Oct ’20–Jun ’21),

‘NEW’ tariffs (Jul ’21–Sep ’21)

\\

Oct–Sep tariff period:

‘NEW’ tariffs (Oct ’20–Sep ’21)

\\

BE:

‘NEW’ tariffs (Oct ’20–Sep ’21)

\\

AT:

‘old’ tariffs (Oct ’20–Dec ’20),

‘NEW’ tariffs (Jan ’21–Sep ’21)

\\

SK:

‘old’ tariffs (Oct ’20–Sep ’21)

2020

Annual yearly capacity

auctions

Early Jul 2020

(PT)

Art. 30:

Publication of tariff

information before tariff

period

(‘NEW tariffs’)

Jun 2020

(ACER)

Art. 36(5):

Deadline for ACER to publish

a report on application of r/p/m-s in MSs

6 Apr 2020

(= EIF + 3 years)

Art. 29: Publication of tariff

information before annual yearly

capacity auctions

Jun 2020

Blue box:

The deadline for ACER to publish a report

on application of RPMs in MSs is calculated as three

years as from the TAR NC’s entry into force, indicated

by the blue box as 6 April 2020.

Grey boxes:

Similar to the grey boxes on the previous

three timelines ‘Calendar year 2017, 2018 and 2019’,

the four grey boxes on this timeline represent the

deadlines for publication of the set of tariff information

before the tariff period. In this year, for almost all the

tariff periods, these are the ‘new’ tariffs following the

‘new’ RPM. The only exception is Slovakia which is not

shown in any of the grey boxes – since the first time for

publishing information before the new tariff period will

only occur in December 2021. The same rule for pub-

lication of tariff information on ENTSOG’s TP applies.

Note that in Austria the information per Article 30 will

be published in December 2020 for the new four-year

tariff period starting on 1 January 2021.

Red box:

This box represents the date of the annual

yearly capacity auctions per CAM NC.

Yellow box:

Similar to the previous two timelines ‘Cal-

endar year 2018 and 2019’, the yellow box represents

the obligation to publish the set of tariff information be-

fore the annual yearly capacity auctions, on TSO/NRA

website (Article 29 of the TAR NC). The same rule on

reserve prices derived following the ‘old’ or ‘new’ RPM

applies (in 2020, only in Austria and in Slovakia these

will be not fully ‘new’ tariffs published before the annu-

al yearly capacity auctions). The same rule applies for

publishing tariff information on ENTSOG’s TP.

Green box:

This box is linked to the green box on the

timeline ‘Calendar year 2018’, and indicates ENTSOG’s

report to ACER on TSOs’ compliance with the TAR NC

Chapters other than Chapter VIII ‘Publication require-