172 |
TAR NC Implementation Document – Second Edition September 2017
MULTI-TSO ENTRY-EXIT SYSTEMS
WITHIN A MEMBER STATE
May
2024
Dec
2017
Apr
2019
May
2019
Jun
2019
Aug
2018
Sep
2018
Oct
2018
Nov
2018
Dec
2018
Jan
2019
Feb
2019
Mar
2019
Figure 51:
Timeline for multi-TSO arrangements within a MS
(NRA)
Art. 28(1):
Deadline to finish the
consultation on ITC
Late Oct 2018
(NRAs)
Art. 27(4)–(5): Deadline to decide on the results
of the final consultation, calculate and publish tariffs,
send the decision to ACER and the EC
31 May 2019
(NRA)
Art. 28(1): Deadline to decide on the results of the
consultation on M, SF, int. Di, LNG Di, ‘isolation’ Di
31 May 2019
(NRA)
Art. 10(2)(a)–(b): Decide on a separate
application of RPM (same/different RPMs)
31 May 2019
(NRA)
Art. 10(5): Deadline to publish ITC mechanism
and cond. responses for consultation on ITC
31 May 2019
(TSO/NRA)
Art. 10(2)(b):
Carry out IA and CBA
(NRA)
Art. 10(2)(b):
Decide who carries out IA
and CBA on intermediate
steps allowing for
separate application of
different RPMs
(TSO/NRA)
Estimated
deadline for the start of
development of the final
consultation document
Late Dec 2017
(ACER)
Art. 27(2)–(3):
Deadline to analyse cons. document,
and publish and send to TSO/NRA and
the EC the results of analysis
Late Dec 2018
Art. 38: APPLICATION DATE 3
31 May 2019
(TSO/NRA)
Art. 26(1), Art.
27(1): Estimated date of
launching the
final consultation and
sending the consultation
documents to ACER
Late Aug 2018
(NRA)
Art. 28(1):
Deadline to publish cons.
responses on M,
SF, int. Di, LNG Di,
‘isolation’ Di
Late Nov 2018
(NRA)
Art. 28(1):
Estimated date of
launching the
consultation on M, SF,
int. Di, LNG Di,
‘isolation’ Di
Late Aug 2018
(NRA)
Art. 10(5):
Estimated date of
launching the
consultation on effective
ITC and its consequences
on the tariff level
Late Aug 2018
(NRA)
Art. 28(1):
Deadline to finish the
consultation on M, SF,
int. Di, LNG Di,
‘isolation’ Di
Late Oct 2018
(TSO/NRA)
Art. 26(3):
Deadline to publish cons.
responses and summary
Late Nov 2018
(TSO/NRA)
Art. 26(2):
Deadline to finish final
consultation
Late Oct 2018