Table of Contents Table of Contents
Previous Page  40 / 58 Next Page
Information
Show Menu
Previous Page 40 / 58 Next Page
Page Background

DECOMMISSIONING INSIGHT

2015

page 40

The weight of a platform will have little effect on some of the expenditure associated with removal, including

removal preparation, vessel mobilisation, sea-fastening, transportation and load-in onshore. This can result in

a larger average cost per tonne forecast for topside removal for the smallest and lightest structures commonly

found in the SNS and Irish Sea regions, compared to larger structures in the CNS and NNS/WofS regions. However,

the cost per platform is significantly lower in the SNS and Irish Sea.

The large range in costs per tonne for both topside and substructure removal seen in the SNS and Irish Sea is

primarily due to the varying approaches to platform removals. Where possible, decommissioning is carried out in

batches or campaigns to maximise efficiency gains and reduce costs. In the SNS and Irish Sea, several operators

plan to remove multiple platforms in one campaign, allowing mobilisation and other fixed costs to be spread

across the structures being removed. Projects at the bottom of the range are typically those included in a batched

approach, while those at the top of the range are typically planned as individual removals.

Figure 21: Historical Variation in the Removal Cost per Tonne Forecasts for Topsides and

Substructures in the Southern North Sea and Irish Sea

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

2011

2012 2013 2014 2015

2012 2013 2014 2015

Topside and

Substructure

Topside

Substructure

Estimated Cost per Tonne (£ - 2015 Money)

Average Forecast Topside Removal Cost Per Tonne

Average Forecast Substructure Removal Cost Per Tonne

Average Forecast Topside and Substructure Removal Cost Per Tonne

Range in Cost Forecasts

Source: Oil & Gas UK

Removal Cost per Tonne

2014 Average

2015 Average

Topsides

£4,000

£4,600

Substructures

£4,500

£4,400