DECOMMISSIONING INSIGHT

2015

page 8

2014 Survey

2015 Survey

Platform well P&A

£2.7million

£3million

Subsea exploration and appraisal well P&A

£5million

£8.8million

Subsea development well P&A

£7.6million

£9.6million

Topside removal cost per tonne

£4,000

£4,600

Substructure removal cost per tonne

£4,500

£4,400

Average Forecast of Costs from 2015 to 2024 in the Southern North Sea and Irish Sea

Some of the average cost forecasts are significantly different to those presented in the 2014 survey. These changes