Background Image
Previous Page  23 / 68 Next Page
Information
Show Menu
Previous Page 23 / 68 Next Page
Page Background

COVER STORY

June 2015

MODERN MINING

21

provided a safer alternative during the devel-

opment of Brakfontein ventilation shafts 2EO

and 6W1.

One option is to first excavate to the rock

level, construct a concrete shaft, which in the

case of Shaft 2EO would have been 20 m in

height and then back-fill to return to ground

level. This is a time consuming and expensive

undertaking.

Using the precast ring system to form the

shaft, MK Africa, was able to back-fill incre-

mentally, which halved the time it would have

taken using conventional methods.

MK Africa’s project scope entailed bulk

excavation and stockpiling of 113 000 m³ of

material to form the boxcut; and 170 m³ of

reinforced concrete for the vent bases. Precast

concrete rings of 4,5 m diameter were used for

Shaft 2EO; and 6,1 m diameter precast concrete

rings to a height of 10 m for Shaft 6W1. The

final phase entailed backfilling and compaction

of the boxcut to a total of 113 000 m³.

MK Africa has used the same technique

successfully on other projects, including

Brakfontein ventilation shaft 2B4 at Bokoni.

This involved the construction of a 38 m deep

ventilation shaft.

“This is an example of how we think ‘out-

side the box’ to add value for our clients. The

simplest solutions are frequently the best,”

points out Venter.

Modikwa No 2 shaft project

A current example is an approximately

11-month bulk infrastructure contract, sched-

uled for completion in June 2015 at Modikwa

platinum mine, which is located some 15 km

north-west of Burgersfort.

The scope of work here has been multi-fac-

eted and includes the construction of terraces

entailing approximately 400 000 m³ of fill mate-

rial to create the final 3 ha platform. The mine’s

new No 2 decline shaft goes into the mountain

at that level.

Also included was the upgrading of a 5 km

gravel access road, together with the installa-

tion of stormwater systems, the building of four

pollution control dams, and the construction of

a ventilation shaft.

Approximately 140 000 m³ of G5 material

was sourced from the existing mine waste

stockpile, with MK Africa carrying out screen-

ing operations on site. Here MK Africa’s

Cat 938K has been the primary loading tool.

This G5 material was used as overlay for the

road reconstruction, as well as for final terrace

surfacing.

Previous work at the mine has entailed bulk

earthworks and civils at Modikwa South 2.

The scope here involved 39 706 m³ of earth-

works; 1 150 m of precast pipe installation; and

283 413 m³ of terrace layer works.

Presently, MK Africa works on a maximum

of three to five contracts in parallel in order to

retain tight management control. “Our goal is

to keep growing to the point that we become

the employer of choice in our niche market, as

we expand MK Africa’s construction footprint

within the Southern African region.

“Whilst the industry is generally under

pressure at present, we at MK Africa have

a reasonable pipeline of work for the near

future and are exploring excellent prospects in

the medium term with our ‘partners’ in both

the mining and industrial sphere,” adds van

Schalkwyk.

Approximately 140 000 m³

of G5 material was sourced

from the existing waste

stockpile at Modikwa dur-

ing MK Africa’s recent bulk

infrastructure contract at

the mine.