Background Image
Previous Page  27 / 68 Next Page
Information
Show Menu
Previous Page 27 / 68 Next Page
Page Background

June 2015

MODERN MINING

25

PLATINUM

at all times when they enter the Booysendal

property. “Putting the whistle on puts us in the

right safety frame of mind and enables us to

alert our colleagues and co-workers to safety-

compromising situations.”

Theron explains that Northam selected

the contract mining approach to diversify its

risk. “Our contract mining adjudication pro-

cess was based on certain criteria. Murray &

Roberts Cementation were not necessarily the

cheapest contractor, but they had – and do still

have – vast experience in mechanised mining.

This was critical in our decision-making pro-

cess.” He adds that the two companies have

established a joint relationship of openness

and fairness.

“When we initially started at Booysendal, our

primary objective was to deliver a 160 000 oz/a

UG2 mining operation and, while we are

approaching this, our objectives have evolved

and our expectations have grown. We will soon

target a monthly production rate of plus 200 000

tonnes per month which would equate to just

below 180 000 oz/a. But I believe the potential

volumes from the UG2 and Merensky mines are

closer to 250 000 oz/a within the next four to

five years,” Theron reveals. This could increase

the size of Murray & Roberts Cementation’s cur-

rent contract on site.

Northam Platinum is current underway with

a feasibility study to determine the viability of

developing and mining Booysendal’s Merensky

Reef. Murray & Roberts Cementation has also

been contracted to mine a bulk sample as part of

the study. “We are extremely positive that this

is just the start of a new mine,” says Theron.

In addition to developing a new Merensky

mine, Booysendal Division intends to increase

its overall PGM output significantly beyond

that and will do so having acquired the Everest

mine from Aquarius Platinum South Africa.

The orebody lies adjacent to Booysendal and

its infrastructure (primarily a concentrator and

equipment) will allow Northam to ramp-up

production quickly. “As an operating asset, it

also provides synergies to exploit our larger

Booysendal South and Central properties,”

Theron observes.

Everest – or Booysendal South as it is to be

re-named – has the potential (with a 230 000

to 250 000 tpm concentrator) to produce

250 000 oz/a of PGMS as well. This means that

by 2020 the Booysendal Division could be pro-

ducing 500 000 oz/a.

Following the Competition Commission’s

approval, Northam will pay R400 million

which places the full ownership of the prop-

erty, infrastructure, equipment, plant and

30 MVA power supply at Everest in its hands.

The final R50 million is payable on transfer of

the mining right to Booysendal.

“We are already assessing some of the

equipment on site and hope within the next

18 months to be generating sufficient tonnages

to validate re-starting the processing facility

which includes a chrome spiral plant which

operated for only a few months before it was

shut down,” says Theron.

Aquarius had also progressed quite far with

an opencast study on the Everest property

which Northam will continue evaluating as

part of its organic growth strategies.

Materials handling

infrastructure on surface.

“We will soon

target a monthly

production rate

of plus 200 000

tonnes per

month which

would equate

to just below

180 000 oz/a.”

Willie Theron, GM,

Booysendal