Simon Storage Ltd – Immingham East Terminal

Gasoline Import – Layers of Protection Analysis

P & I Design Ltd

DOCUMENT NO: SI057001_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: G DATE: 29.06.12

Tel: + 44 (0)1642 617444

PAGE 28 OF 34

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

Other causes not assessed in detail as their contribution is significantly lower than causes 1

through 3.

Cause

Description

Notes

4

Valve failure (or

passing) on a route

where import is not

expected.

All routes have at least two isolation valves with

automated tank inlet valves. Probability of this failure

leading to an overfill is very low compared to other

initiating events.

6

Changes in the filling

rate due to changing

operations on other

tanks.

Not considered as an issue, as only one tank is filled at a

time. The maximum quoted rate for a ship import is

250te/hr (333m

3

/hr)

7

Failure to terminate

filling at the ship on

request from terminal

The ship operators and ISCo operations are monitoring

the transfer and will normally stop at the required parcel

quantity. Contact is made with the ship operations to

warn that the tank is reaching its required quantity. The

ship is highly unlikely to export more than the

contracted quantity.