GAZETTE
APRIL 1986
English Case Law
A series of English cases in the House of Lords dealt
with this particular problem of accrual. Various formulae
were applied to suggest the point from which time should
run. In
Sparham-Souter
it became when the occupier
knew or ought reasonably to have known of the damage.
In
Anns
v.
Merton
it was where the defect became a
present and imminent danger. In
Pirelli
v.
Faber
it was
adjusted to the point in time where the actual damage
was caused. In the
Pirelli
formula reliance would be
placed on technical evidence to locate the actual point
in time when damage occurred whether discoverable or
not and the limitation period would begin to run from
then. In that case the plaintiff lost his claim because 6
years had expired from the date of actual damage before
a writ was issued and he was held to be statute barred.
If the "discoverability" test had been retained this
problem would not have arisen.
In England, this has led to competing claims for the
plaintiff and the defendant. The balance had to be struck
between the injustice of the plaintiff losing the right to
sue with the unenviable position of a defendant faced with
the mischief of old claims which the Statute of
Limitations was designed to cure. The courts have given
three differing reasons supporting the existence of statutes
of limitations, (1) that long dormant claims have more
of cruelty than justice in them, (2) that a defendant might
have lost the evidence to disprove a stale claim and (3)
that a person with a good cause of action should pursue
it with reasonable diligence, but the dilemma in the latent
damage cases in England since
Pirelli
is that the plaintiff
might lose his chance to sue before he knew he had
suffered loss.
The vexed state of the law in England on the question
of limitation of time and negligence has led to pressure
for corrective legislation. Consideration is being given to
a Report on Latent Damage of the Law Reform
Committee
5
which was issued to provide recommendat-
ions in this area. This Report proposes that there should
be no change whereby a cause of action in negligence
accrues on the date of damage in the ordinary case where
the damage is obvious form the date of its occurence.
Secondly, if the damage arises from latent defects in
negligence cases then the plaintiff should be given a
limitation period of 3 years from the date of discovery
(or from when discovery could have been reasonably
made) of significant damage. This would be a new
"discoverability" test giving 3 years in which to sue for
significant damage. The "discoverability" test would be
subject to a long stop of 15 years running from the date
of the breach of duty in order to avoid the negligent
designer or builder being available as a mark to sue in
perpetuity. This would mean that there could be no court
action more than 15 years after a breach of duty.
This report has received a poor welcome by the building
industry in England
6
as being too much in favour of
the plaintiff. But the problem is intractable. On any
objective analysis the proposed legislation is generally
seen as a compromise which could lead to injustice on
either side because occasionally latent damage might not
become obvious until after the 15 year period had expired
so that a Plaintiff could not sue while on the other hand
the prospect of defending a case some 15/20 years after
completion is repellent for reasons already stated.
Morgan v. Park Developments Ltd.
In Ireland, the clearest expression of the law applicable
is in the judgement of Carroll J in
Morgan
v.
Park
Developments Ltd.
Here the plaintiff bought a house
from the defendants - who were builders - in 1962. The
plaintiff noticed defects soon after moving in and these
were repaired by the builders. One large crack was
repaired for a second time in 1965 (the eventual date
chosen by the Court from which time ran) and in 1975
the crack repair was attempted again by a different
builder. It was only in 1979 i.e. 17 years after purchase
that an Architect was consulted who reported a major
structural fault. Proceedings were issued in 1980 and the
judgement was in 1983 or 21 years after the sale of the
house.
It was held that the date of accrual in the action for
negligence was the date the defect either was discovered
or should have reasonably been discovered and that
neither date of accrual would be sufficient to bring the
plaintiffs claim within the six year period allowed by the
Statute of Limitations 1957. Hence the builder was not
liable. The similarity in the test adopted by the learned
Judge to the
Sparham-Souter
test and to the test proposed
by the LRC has been noted.
Although there was no liability on the builder on the
facts of this case, the combined effects of the accrual test
based on "discoverability" adopted by Carroll J and the
earlier LRC proposals to the same effect have caused
noticeable anxiety in the building industry in its various
sectors.
Submissions have been made to the Minister for the
Environment/Justice to highlight the problem of stale
claims for defendants. It is difficult to see how a
completely just compromise can be achieved because of
the conflicting interests of the plaintiff and defendant,
but a solution will have to be found in the legislature.
The absence of any "discoverability" test in the case of
personal injuries is notorious, in circumstances where the
plaintiff has only 3 years in which to sue. Common
wisdom is that a re-appraisal of the whole question of
accrual of the cause of action in all negligence cases is
almost inevitable.
Many people see any possible legislation on latent
defects as raising solutions through compulsory insurance
against damage. A dispassionate analysis of the latent
damage problem together with insurance possibilities has
been propounded in England by a recent Report
7
prepared by Atkins Planning for the Building Economic
Development Committee (EDC) acting through a non-
binding Insurance Feasibility Steering Committee. The
terms of reference which apply to the Report were to
investigate the feasibility of latent defects protection
insurance for all new building save housing, and to make
recommendations to the Building EDC on their findings.
The Report took four central considerations into
account (a) that "defects have many roots other than
breaches of contract and negligence" i.e. freak storms
for instance, and (b) that liabilities and responsibilities
for latent defects are confused because "English Law on
construction liability is a mess" and (c) that building
producers are liable only to their immediate clients in
contract and they note that actions in tort, which is the
only path open to a subsequent owner, are more
90