Previous Page  104 / 330 Next Page
Information
Show Menu
Previous Page 104 / 330 Next Page
Page Background

GAZETTE

APRIL 1986

that the British Standard in Bridge Building No.540C

(B.S. are normally taken as deemed to satisfy in Irish

building bye-laws) is the only B.S. assuming a required

nominal design life - in that case 120 years. The code also

assumes ongoing maintenance and repair. On the other

hand, a mineralised felt finish provided on a typical built-

up factory roof would have only a one year guarantee

as laid with perhaps a ten year life span. In essence the

questions of durability and maintenance are integral and

the building owner who neglects maintenance and repair

is inviting minor latent defects to become major patent

damage. The study of life cycle costing of buildings and

materials is now advanced enough to offer a statutory

defence based on the life expectancy of various building

materials and methods of construction.

The building industry can point to the Directive of the

EEC Council of July 1985 regarding liability for defective

products as an example providing for statutory defences.

This directive will not include buildings but it will include

some building materials and building products erected by

sub-contractors on site. Article 7 envisages defences

including a "state of the a r t" defence i.e. that the state

of technical knowledge at the time the product was put

into circulation was not such as to enable the existence

of the defect to be discovered. This Directive, which

includes a requirement that the Member States shall bring

into force a national law within three years in order to

comply with its provisions, contains alternative forms of

possible national legislation of vital interest to the Irish

building industry and its customers.

Regardless of which alternative legislation is enacted

(let Irish builders and sub-contractors be warned) the legal

consequences on site could lead to further confusion given

the present uncertainty on latent defects and the varying

degrees of responsibility which the law imputes on

members of the building team. The variation in the

standard of care required on a typical commercial but

non-housing development using the 1977 yellow Form of

Contract (with quantities) of the Royal Institute of

Architects of Ireland will then be on three levels as follows

(a) for the Consultant designers the standard of care will

be that of a reasonable member of his own profession

and (b) the standard for the Contractor will be good work

and proper materials and (c) the standard for certain as

yet unspecified building materials supplied, fabricated,

delivered and erected on site will be subject to future

legislation which the EEC directive requires to be passed

by July 1988. This legislation is likely to lead to a standard

of care closer to strict liability for these products but

statutory defences will be available as explained.

It is easy to visualise a site situation where the

Architect/Engineer designs and the Contractor builds into

a fabrication supplied and erected by a sub-contractor

in accordance with the design. This could arise for

instance in building - in mechanical and electrical services-

which of their nature have a shorter working life than

the materials of construction such as brick and timber.

Latent defects turning into discoverable damage in that

situation is duly bound to create further disorder and

uncertainty in the field of construction law.

The existing legal circumstances in this area present an

opportune time to introduce an imaginative Bill to

accomodate an agreed solution to the problems outlined.

There will be no shortage of ideas. The building industry

would be concerned if such legislation included the

imposition of new duties based on a concept of "fitness

for purpose" in non-housing contracts. Even with

statutory defences avialable there is a fear that this could

eventually lead to the acceptance of a building as " a

product" in legal terms. Thus "fitness for purpose"

today might mean strict liability tomorrow.

"Fitness for purpose" is a concept borrowed from sl4

(1) of the Sale of Goods Act 1893 where it is an implied

condition as to quality. The reported building cases leave

no doubt that the concept means more than just providing

a premises using good materials and p r oper

workmanship. The term "fitness for purpose" itself

denotes the giving of an implied assurance beyond the

level of a duty to use a reasonable skill on the part of

the designer and beyond the duty to use proper materials

and workmanship on the part of the builder.

Summons Servers Ltd.

Internationally represented in over 40

countries.

Summons Servers Limited is available for

service of all Court Documents, Summons,

Petitions, Citations, Probate, Debtors

Summons t hroughout Ireland and under

Order 11 R.S.C. for Out of Jurisdiction Cases

on a wo r l dw i de basis.

Ri chmond Chambers,

101 Ri chmond Road,

Drumcondra, Dubl in 3.

Tel: 3 6 0 1 2 4 / 5 - 371906.

A subsidiary

of K Security

Private

Investigations

Ltd

Professional Information

continued from page 102.

Lost Title Deeds

Premises: 72 Amiens Street, Dublin. Will anyone knowing of the whereabouts

or having any information concerning the Title Deeds of the above premises pur-

chased by the Trustees of Fianna Fail, Dublin Central Comhairle in or around

1955, please contact Devaney & Ryan, Solicitors, 53 North Strand Road, Dublin

3. Telephone: 746500.

The Profession

MARY M. FOLAN, B.A., H.D.E., Solicitor, Commissioner for Oaths,

wishes

to announce that she has commenced practice under the style of Folan & Co.,

at 33 Capel Street, Dublin 1. Tel.: (01) 786933.

Solicitors required for progressive new law firm.

General Practice. Excellent prospects.

Tel.: 694766 Unit 1201

94