Project Engineer SKANSKA WALSH Design-Build Joint Venture LaGuardia A rport CTB Replacement Project Hangar 5A Runway Drive Flushing, NY 11371 Mobile: (917) 565-6140 Think twice before you press "print."
This message, including any attachments hereto, may contain privileged or confidential information and is sent solely for the attention and use of the intended addressee(s). If you are not an intended addressee, you may neither use this message nor copy nor deliver it to anyone. In such case, you should immediately destroy this message and kindly notify the sender by reply email. Thank you. From: Andee < andee@spearheadcx.com> Sent: Thursday, December 19, 2019 1:06 AM Cc: Sean
Hello everyone,
Given the holiday and postponed meeting next week, wanted to send quick recap of this Tuesday's planning meeting for everyone. If I've missed anything, please feel free to correct. Also, Gary shared there's a little heat in some spots on the bridge. Thank you.
Week
Accountable Event
Notes
9-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 23-Dec-19 23-Dec-19 23-Dec-19 23-Dec-19 30-Dec-19 30-Dec-19 2-Jan-19 13-Jan-19 13-Jan-19 20-Jan-19 20-Jan-19
SWJV Temp Wall
Level 2 - Temp Wall Built
Sean Gary SpCx Zack
Update progress Accept delivery Start 2nd Shift Schedule shipment
Plasterform Shops marked up and distributed to Zack and Bill
Delivery scheduled for 18 Dec 19 @ 9am
Crew size of 8
GFRG/C delivery prior to Friday; Existing crates for areas @ moving walkway and ends of flares
Bill
Clear area
Brooklyn Diner for lifts
SWJV Remove boards
Level 4 - Remove PBB side this Saturday to take a look
Bill
Scrape Monokote BR line at Col B6 to get the Capitals in place
Gary Sean
Send photos Submit RFI
Photos to Zack and Sean - East side blocking
RFI - Vertical Fireblocking
SWJV Temp Wall SWJV Inspection
Level 3 - Starting on Temp Wall
Staircase Walls Inspection (17 Dec 19); Should be able to close pending inspection
SpCx
Begin framing Begin framing
East Side feature wall
Others
Fire Shutter
SpCx SpCx
Ongoing
Continue installing black iron, GFRG/C, Frame, Rock and Tape/Finish
Begin framing
Nor h and Sou h East side can be framed
SWJV Protect space
Tarps up to keep installed wall boards and GFRG/C dry
Bill
Provide heat
Temp electric heaters installed; Bill to coordinate w electricians; Temp needs to stay > 40 degrees; Bill has access to 12 electric heaters
SpCx
Start ceiling
Above escalator
Others
Elevator
Elevator door jambs arrive
SWJV Remove wall
Level 2 - Wea her wall removed
Others
Elevator
Elevator fronts arrive; Park cars 3rd floor for elevator Brooklyn Diner Ceilings need to be complete Radiators done (critical for GFRG covers install and finish)
SpCx SpCx
Finish ceilings Finish radiators
SWJV Provide heat SWJV Remove wall
Permanent heat 3rd week Jan
Level 4 - Temp wall removed (latest)
tbd tbd tbd
Existing Temp Wall Existing Temp Wall Existing Temp Wall
Donaldson to help brace exis ing Temp Wall; Possibly tie into extisting wall Plan A --> Submit drawings as designed; Remove and build as designed
Plan B --> Remove and salvage the bracing
Take care,
-Andee Andee Hidalgo Owner & President Spearhead Construction, LLC MBE | WBE | SDVOB | SDVOSB | PANYNJ | NYCSBS