Project Engineer SKANSKA WALSH Design-Build Joint Venture LaGuardia A rport CTB Replacement Project Hangar 5A Runway Drive Flushing, NY 11371 Mobile: (917) 565-6140 Think twice before you press "print."

This message, including any attachments hereto, may contain privileged or confidential information and is sent solely for the attention and use of the intended addressee(s). If you are not an intended addressee, you may neither use this message nor copy nor deliver it to anyone. In such case, you should immediately destroy this message and kindly notify the sender by reply email. Thank you. From: Andee < andee@spearheadcx.com> Sent: Thursday, December 19, 2019 1:06 AM Cc: Sean ; Corallo, Frank ; Trause, Zachary ; Carson, Bill ; Bilgen, Murat Subject: Spearhead Tuesday Planning Meeting Follow up [External Email]

Hello everyone,

Given the holiday and postponed meeting next week, wanted to send quick recap of this Tuesday's planning meeting for everyone. If I've missed anything, please feel free to correct. Also, Gary shared there's a little heat in some spots on the bridge. Thank you.

Week

Accountable Event

Notes

9-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 16-Dec-19 23-Dec-19 23-Dec-19 23-Dec-19 23-Dec-19 30-Dec-19 30-Dec-19 2-Jan-19 13-Jan-19 13-Jan-19 20-Jan-19 20-Jan-19

SWJV Temp Wall

Level 2 - Temp Wall Built

Sean Gary SpCx Zack

Update progress Accept delivery Start 2nd Shift Schedule shipment

Plasterform Shops marked up and distributed to Zack and Bill

Delivery scheduled for 18 Dec 19 @ 9am

Crew size of 8

GFRG/C delivery prior to Friday; Existing crates for areas @ moving walkway and ends of flares

Bill

Clear area

Brooklyn Diner for lifts

SWJV Remove boards

Level 4 - Remove PBB side this Saturday to take a look

Bill

Scrape Monokote BR line at Col B6 to get the Capitals in place

Gary Sean

Send photos Submit RFI

Photos to Zack and Sean - East side blocking

RFI - Vertical Fireblocking

SWJV Temp Wall SWJV Inspection

Level 3 - Starting on Temp Wall

Staircase Walls Inspection (17 Dec 19); Should be able to close pending inspection

SpCx

Begin framing Begin framing

East Side feature wall

Others

Fire Shutter

SpCx SpCx

Ongoing

Continue installing black iron, GFRG/C, Frame, Rock and Tape/Finish

Begin framing

Nor h and Sou h East side can be framed

SWJV Protect space

Tarps up to keep installed wall boards and GFRG/C dry

Bill

Provide heat

Temp electric heaters installed; Bill to coordinate w electricians; Temp needs to stay > 40 degrees; Bill has access to 12 electric heaters

SpCx

Start ceiling

Above escalator

Others

Elevator

Elevator door jambs arrive

SWJV Remove wall

Level 2 - Wea her wall removed

Others

Elevator

Elevator fronts arrive; Park cars 3rd floor for elevator Brooklyn Diner Ceilings need to be complete Radiators done (critical for GFRG covers install and finish)

SpCx SpCx

Finish ceilings Finish radiators

SWJV Provide heat SWJV Remove wall

Permanent heat 3rd week Jan

Level 4 - Temp wall removed (latest)

tbd tbd tbd

Existing Temp Wall Existing Temp Wall Existing Temp Wall

Donaldson to help brace exis ing Temp Wall; Possibly tie into extisting wall Plan A --> Submit drawings as designed; Remove and build as designed

Plan B --> Remove and salvage the bracing