Article 2: Administration

Section 2.5. Application-Specific Review Procedures

2.5.3. Rezoning

Morrisville, NC

June 23, 2017

Unified Development Ordinance

Page 2-29

and maps. Unless accompanied by an application for Conceptual Master Plan Approval

(Section

2.5.4)

, a Conditional Rezoning application shall include a sketch plan.

c.

A Planned Development Rezoning application may be submitted only by the owner(s) of the

property or properties proposed to be rezoned or a person duly authorized to submit the

application on behalf of the owner(s). The application shall include a PD Plan/Agreement that

depicts the general configuration and relationship of the principal elements of the proposed

development (uses, intensity, circulation, open space, public facilities), outlines how the

development will be phased and served by public facilities, and provides for unified

management. (See Section

3.7.1.E.1, PD Plan/Agreement.

)

d.

The applicant for a General Rezoning application may only change the application into a

Conditional Rezoning application by withdrawing the General Rezoning application before

provision of or final arrangement for required notice of the public hearing meeting and

submitting an application for Conditional Rezoning. The Conditional Rezoning application is

subject to additional application fees to defray the additional processing costs.

Staff Review and Recommendation

The Planning Director shall review the application, allow revisions of the application, and prepare

a staff report and recommendation in accordance with Sectio

n 2.4.4.

Scheduling and Public Notice of Meetings

The application shall be scheduled, and required public notices provided, for Planning and Zoning

Board and Town Council meetings in accordance with Section

2.4.5.

Planning and Zoning Board Review and Recommendation

The Planning and Zoning Board shall review the application, hold a public comment session, and

make a recommendation in accordance with Section

2.4.6,

except that the recommendation shall

address whether the proposed rezoning is consistent with the Comprehensive Plan, and the board

shall take action on the application for a General Rezoning within 60 days after the meeting at

which it first reviews the application—provided, however, that the board may vote to extend this

time period to up to 90 days for good cause.

Town Council Review and Decision

The Town Council shall review the application, hold a standard public hearing, and decide the

application in accordance with Section

2.4.7,

subject to the following provisions.

a.

A decision on a General Rezoning application shall be one of the following:

(1)

Approve the application as submitted;

(2)

Approve a rezoning to a more restrictive district, with the applicant’s consent;

(3)

Deny the application; or

(4)

Remand the application back to the Planning Director or Planning and Zoning Board for

further consideration. (This may require further public notice and additional review fees.)

b.

A decision on a Conditional Rezoning application shall be one of the following:

(1)

Approve the application as submitted (including any conditions proposed as part of a

Conditional Rezoning application);

(2)

Approve the application subject to modified or additional conditions, with the applicant’s

consent;

(3)

Deny the application; or