Previous Page  23 / 52 Next Page
Information
Show Menu
Previous Page 23 / 52 Next Page
Page Background

December 2016

MODERN MINING

21

GEOTECHNICAL

ENGINEERING

The installation of the drap-

ing systemwas managed

by Fairbrother Geotechni-

cal Engineering using

their own employees and

supplemented by seven rope

access technicians (RATs)

provided by Alpinist Safety

Consultants (ASC).

For that reason industrial rope access tech-

niques were proposed to the mine with the

additional sub-contract appointment of a spe-

cialist company, Alpinist Safety Consultants

(ASC), with a track record of successfully and

safely executing difficult drape system installa-

tions in the civil engineering market.

The Geobrugg Rockfall Drape design soft-

ware was used to determine the most suitable

and economical solution which resulted in a

number of draping options being discussed

and a solution negotiated with the client to fit

the budget allocated for this slope. The final

solution was a combination of 16 500 m

2

of

QUAROX

®

rolled cable nets (3,9 m x 30 m per

roll) overlayed by DELTAX

®

mesh (secondary).

The superior qualities of QUAROX rolled

cable nets compared to conventional cable

nets allowed for easier and more efficient

installation. No extra work was required

before unrolling down the slope which pro-

vided for a 30 % reduction in installation

time. The QUAROX fits unobtrusively on

the slopes and can be colored using powder

coating to give it an even better visual appeal.

The chain link construction of the cable nets

offers much better force transmission than

traditional connection by cross clip. Standard

support ropes, seaming ropes and shackles

are used for the installation.

This project was a first as the QUAROX Plus

drape system had not previously been used in

an application in the mining sector in Africa.

The installation of the draping system

was managed by Fairbrother Geotechnical

Engineering using their own employees and

supplemented by seven rope access technicians

(RATs) provided by ASC. The proximity of a

haul road at the top of the slope allowed for

the provision of track-mounted crawler rigs to

install the anchor system for the drape mesh

at the crest of the slope. This haul road further

enabled Fairbrother to provide a more efficient

service to the technicians by using a crane to

lower the mesh panels into place before send-

ing the RATs down the slope to fasten the

panels into place.

Additionally, to assist the mine with its

desired use of the trolley line, a 2 m high berm

was constructed in the middle of the road as an

exclusion barrier allowing for the trucks to con-

tinue hauling payload up the trolley line whilst

the RATs installed the drape mesh.

Safety was of paramount importance to all

the parties and was a non-negotiable on this

project. The fast installation methods required

that three self-contained teams of RATs work

on the slope at the same time clipping the mesh

panels together and it was vitally important

that there was never a ‘crossover’ between the