Previous Page  22 / 56 Next Page
Information
Show Menu
Previous Page 22 / 56 Next Page
Page Background

CONSTRUCTION WORLD

JULY

2017

20

and subsequent further consultation after

our appointment, crucially meant that the

works started towards the beginning of

the wet season rather than, as had been

expected, at the beginning of the dry

season,” Pearce says.

This turned out to be one of the central

challenges of the project. “The timing of the

commencement of the works has caused

major access problems for main contractor,

Group Five, which has had to contend with

the mighty Tugela River regularly flooding

the access causeway during the wet season

– even during the current ‘drought’ in South

Africa,” says Pearce. “The access causeway

has been washed away several times with

equipment having to be moved off position

each time in anticipation. Fortunately,

there have been no injuries and no major

equipment has been lost because of these

precautionary measures.”

Franki’s scope of work includes the

installation of 48 no. 1 100 mm diameter

permanently cased oscillator piles. The

bridge deck is approximately 165 m long

and piles are required to support both the

north and south abutment and all 5 no.

intermediate piers with 6 no. piles per pier

raked at 1 in 6 and 6 no. vertical and 3 no.

raked piles per abutment.

The geotechnical data available indicated

typical river bed conditions with gravels,

sands and boulders up to 1,5 m in diameter

in layers above soft to medium rock

overlying hard to very hard rock. Fractures

in the rock resulted in the tender design

requiring 1,4 m rock sockets and dowelling

into the rock below every pile.

“Historically, river bridge piles requiring

sockets are slow to construct using driven

or screwed-in casings and ‘smash and grab’

techniques to form piles and sockets in

rock. The slow pace not only increases costs

but also increases the risks associated with

working in a river. We therefore opted for

oscillating casings down to rock level and

then using a cluster drill – a multi-headed

percussion hammer – for the rock drilling.

This solution has reduced construction time

by over 50%,” Pearce says.

He adds that the increased performance

of the cluster drill has enabled Franki to use

a longer socket length in lieu of the dowels,

saving further time and cost.

Both the oscillator and cluster drill are

mounted on Franki’s Bauer BG28 piling rig,

which has an operating weight of about

reinforced concrete bridge adjacent to the

existing steel structure. “This was a good

solution,” says Paul Pearce Franki Africa

KZN branch manager, “as it meant that

use of the existing bridge has not been

interrupted during construction.”

Pearce says that the Tugela Ferry area

has historically been a political hot-spot and,

as a result, the award of the main contract

was a lengthy process which involved

extensive consultation with all the relevant

local parties on their involvement in the

project. Ultimately, in June 2016, Franki was

appointed specialist subcontractor for the

piling works for the new bridge.

“The prolonged award of the contract

COVER STORY

FRANKI’S INNOVATIVE SOLUTIONS

help to bridge KZN community

Installation of raked pile temporary

casing through gravel, sand and

boulder layers.

People struggle to make a living in Tugela

Ferry and the harsh conditions were, for

many years, exacerbated by the town being

split by the Tugela River and connected only

by an inadequate single-lane bridge, the

Tugela Ferry Bridge, which has significantly

slowed the local economy by hampering

vehicular movement and has been a threat

to the lives of the multitude of pedestrians

that have had to share the bridge with cars,

tractors, bakkies, trucks and more.

Franki’s geotechnical solution

The KZN Department of Transport therefore

embarked on a project to widen the bridge

to two lanes by constructing a new,

The tiny town known as Tugela Ferry (named after the ferry that used to

connect the two halves of the town) in the local Municipality of Msinga,

part of the Umzinyathi District Municipality in central KwaZulu-Natal is

part of one of South Africa’s most impoverished areas.