Previous Page  23 / 56 Next Page
Information
Show Menu
Previous Page 23 / 56 Next Page
Page Background

21

CONSTRUCTION WORLD

JULY

2017

Franki Africa is part of the

Keller group, the largest

independent geotechnical

contractor in the world.

Pier 2 piles trimmed in preparation

for pile cap construction.

Piling for the bridge piers on the

new Tugela Ferry River Bridge.

90 tons and is ideally suited for the Tugela

Ferry piling solution.

“We owe a lot to the BG28 which has

enabled Franki to implement many cost-

efficient solutions to a wide range of clients

since it first arrived in this country from

Germany in 2012,” Pearce says.

Another time-saving solution used by

Franki was the construction of a movable

ramp to create the required 1 in 6 rake,

meaning that it is not necessary to modify

the platform earthworks for each pile. “With

all six pier piles raking in different directions

this represents a major cost and time saving

solution,” Pearce says.

Dealing with the unexpected

The necessary raised platform and variable

rock levels, resulted in suitable founding

rock only being encountered at depths of

over 25 m for some piles – 10 m deeper than

the average expected – but piling production

has still met expectations. “The BG28 has

comfortably dealt with deep boulder layers

and, as expected, the cluster drill has formed

sockets in vastly reduced time,” Pearce says.

It was not all plain sailing, however, and

one operational disadvantage has been that

the hard boulders and rock have caused

extreme wear on cutting teeth and bits,

which have required regular maintenance

and replacement.

Another disadvantage has been that when

forming the socket with the cluster drill,

the rock in which the socket is created

is reduced to small chips and dust. This

means that the rock quality is more difficult

to assess post-drilling and a thorough

geotechnical investigation is essential prior

to construction. “As with most geotechnical

works, the cost of a thorough geotechnical

investigation is easily recovered during

construction through design and

construction cost savings, for the ultimate

clien,” Pearce says.

Conclusion

With several lengthy work stoppages due

to flooding of the access causeway, the

piling is expected to be completed in mid-

July 2017.

Following on, the main contractor will

complete the abutments and bridge piers

and place the precast beams supporting

the new deck providing a safe, dual lane link

between the north and south banks of the

Tugela River and helping to uplift Tugela

Ferry and the entire surrounding area.