44 |
Central Eastern Europe GRIP 2017
Figure 4.3:
CEE Region N-1: HR
Cross-border Entry/Exit capacity 2017 (EP_IN / XP_OUT)
Cross-border Entry/Exit capacity – planned 2018-2026 (EP_IN / XP_OUT)
UGS/Production Entry Capacity (S / P) – withdrawal
UGS Exit Capacity (S_X) – injection
Domestic Exit Capacity required for Demand (D_MAX / D_AS)
HR1
Main Supply Corridor for HR
HR2
2
nd
Supply Corridor for HR
CZ
SK
HU
SI
PL
BG
HR
DE
AT
RO
2023
2018
2023
HR1 HR2
2020
4.2.3 CROATIA (HR)
Croatia has two gas supply corridors. The main supply corridor is through Slovenia
(at the figure marked HR1). The second one is through Hungary (marked HR2).
Both supply corridors are for domestic demand at the moment. After the Croatian
LNG terminal (2018) and the Ionian-Adriatic Pipeline (2023) are built, Croatia can
then become a transit country.