Central Eastern Europe GRIP 2017

Figure 4.3:

CEE Region N-1: HR

Cross-border Entry/Exit capacity 2017 (EP_IN / XP_OUT)

Cross-border Entry/Exit capacity – planned 2018-2026 (EP_IN / XP_OUT)

UGS/Production Entry Capacity (S / P) – withdrawal

UGS Exit Capacity (S_X) – injection

Domestic Exit Capacity required for Demand (D_MAX / D_AS)

HR1

Main Supply Corridor for HR

HR2

2

nd

Supply Corridor for HR

CZ

SK

HU

SI

PL

BG

HR

DE

AT

RO

2023

2018

2023

HR1 HR2

2020

4.2.3 CROATIA (HR)

Croatia has two gas supply corridors. The main supply corridor is through Slovenia

(at the figure marked HR1). The second one is through Hungary (marked HR2).

Both supply corridors are for domestic demand at the moment. After the Croatian

LNG terminal (2018) and the Ionian-Adriatic Pipeline (2023) are built, Croatia can

then become a transit country.