Background Image
Previous Page  27 / 72 Next Page
Information
Show Menu
Previous Page 27 / 72 Next Page
Page Background

25

CONSTRUCTION WORLD

AUGUST

2015

PROJECTS AND CONTRACTS

Head of eThekwini Water and

Sanitation (EWS), Ednick Msweli,

said this week that this important

milestone indicated that the city’s

biggest ever bulk water pipeline project was

on target for completion in 2017.

The completed segment of pipeline,

which took a total of 24 months to put in

place, comprises the first two contracts of

the R1,8-billion second phase of the Western

Aqueduct (the estimated overall cost of the

second phase of the WA and associated

branch pipelines is R1,8-billion in present day

terms). The first phase of the Western Aque-

duct, which measures 20 km and stretches

from the Umlaas Road Reservoir to Inchanga,

was commissioned at the end of 2012.

Project manager, Martin Bright, said that

pressure testing of the pipeline that extends

7 km from Inchanga Station to Alverstone

Reservoir was underway and that Cycad

Construction was expected to hand over the

project to EWS during July.

He added that many residents in the

Bothas Hill area, particularly those living

at the bottom of the valley near the Inanda

Dam, who had been under constant water

supply pressure, would enjoy a more

consistent supply of water as soon as the

pipeline was fully operational.

The second contract between Alverstone

Bright. Construction is expected to take 18

months with completion expected towards

the end of 2016.

Msweli said that these achievements

by contractors on behalf of EWS were

significant and ensured that the eThekwini

region had some of the best bulk water

infrastructure in the region. “The Western

Aqueduct is intended to both replace and

augment existing infrastructure that brings

water into Durban from the Midmar and

recently constructed Springrove Dams. The

Western Aqueduct is expected to significantly

strengthen the capacity of bulk water supply

and meet the needs of the greater eThekwini

region for the next 30 years.”

The Western Aqueduct project has

been designed and is being monitored by

the Knight Piesold/Naidu Consulting/Royal

Haskoning DHV Joint Venture.

Significant

MILESTONES

reached

The 14 km stretch of

water pipeline extending

from Inchanga Station to

Alverstone Reservoir and

then on to Ashley Drive in

Kloof is now complete and,

following the conclusion

of pressure testing and

commissioning, will be

handed over to eThekwini

Water and Sanitation (EWS)

and brought into service.

Reservoir and Ashley Drive in Kloof, that has

been completed by WK Construction, has

been successfully tested and is due to be also

handed over to EWS in July.

Bright thanked residents for their

patience during construction and pointed

out that motorists would not only notice

that roadworks were complete but that all

roads excavated to lay the pipe had been

completely rebuilt in places.

Bright confirmed that the third contract

that will see the remaining 25 km of pipeline

laid from Ashley Drive to Ntuzuma is already

well underway. He said that the contractor,

Esor Construction, would be entering one of

the more challenging parts of this project as

it excavated the through fare near the Kloof

Station in order to lay the pipeline.

He said this would lead to some traffic

congestion and confirmed that road works

would continue until 2017. Road closures and

detours will be clearly sign posted.

Another project milestone has been

reached is the awarding of a fourth

contract for construction of an urgently

needed branch line running along Haygarth

Road and under the N3 to Tshelimnyama to

Esor Construction.

This 16 month long contract, worth

R88-million, is expected to relieve water

shortages in the Tshelimnyama area. It will

entail laying a pipeline with a diameter of

600 mm from the entrance to Makaranga

Lodge to the Haygarth Road Reservoir. From

there, a 500 mm pipe will take water to the

existing reservoir in Tshelimnyama.

This contract entails laying 8 km of pipe,

crossing under the N3 at the Marianhill Toll

Plaza. However, according to Bright, there

will be no disruption to traffic or visible

construction work affecting the N3. Esor

Construction will construct a pipe jack that

will push a 90 metre long concrete sleeve

under the N3. The new water pipe will be

inserted into this.

He added that work by Icon Construction

on the Ashley Drive break pressure tank was

progressing well. On completion during the

third quarter of 2015, it is expected to hold

20 mega litres of water.

Tenders have closed for the construction

of the Wyebank Break Pressure Tank and

EWS is currently assessing bids, according to

The photographs show road closures in Intengu

Road in Kloof. Patrols are in place to assist

traffic where roads close due to the Western

Aqueduct pipeline construction.

>

shopping centres. It is targeted to be the

point of first call for convenience shopping,

while the piazza is set to be a unique public

and meeting place with top end restaurants,

beauty and pampering outlets, as well as

other service offerings,” he added.

Central Square will be anchored by an

exceptional line up of grocery shopping from

Pick n Pay, Woolworths Food and SuperSpar.

Pretoria’s only Virgin Active Classic Gym

is its fourth anchor. It will also feature 88

hand-picked speciality stores and branches

of major banks.

For its distinctly delicious dining, restau-

rants already committed at Central Square

include Tasha’s, Koi, Bistro, Turn ‘n Tender,

Mythos, Remos, Frank’s and Fego. They

will be joined by several other cafes, coffee

shops, patisseries and eateries.

Central Square will also have around

1 800 basement parking bays and 300 open

parking bays, enhancing its ease of access,

convenience and pedestrian linkages into the

surrounding precinct.

Located minutes away from the N1

motorway’s Atterbury and Garsfontein inter-

changes, Central Square is right off the main

arterial of January Masilela Road, and a mere

500 metres from the main entrance of the

Menlyn Park Shopping Centre.

I