Background Image
Previous Page  33 / 72 Next Page
Information
Show Menu
Previous Page 33 / 72 Next Page
Page Background

31

CONSTRUCTION WORLD

AUGUST

2015

PROJECTS AND CONTRACTS

at the final level in order to provide a safe

working platform for the installation of the

foundation piles,” says Oldknow.

Choice of piles critical

Naturally the choice of piles in any geotech-

nical project is critical. “Given the depth of

the kaolin, Franki Driven Cast-in-Situ piles

(Franki piles) were preferred to Continuous

Flight Auger (CFA) piles as the more efficient

solution. This was mainly because the Franki

pile’s founding could be achieved at a shal-

lower depth by forming an enlarged base at

the toe of the pile,” says Oldknow.

He adds that the CFA piles (which were

used for the soldier piling) would have to

have been installed at a considerable depth

given the weak shear strength of the kaolin

and would have required the removal of

the spoil material from the final basement

excavation level.

Franki had a 35-week programme from

21 July 2014 to completion 27 March 2015,

which included the lateral support, bulk

excavation, dewatering and foundation

piling. “In spite of the normal Claremont

winter rains, which are always challenging

given the Kaolin soil conditions, we are on

time in terms of anticipated completion

date. In fact we have managed to provide an

earlier start for the building contractor by

giving partial handover of half the completed

pile layout, which allows the contractor to

overlap with our contract providing them

with a two to three week head-start on their

contract programme.

“While there have been many challenges

on this project, we have been able to move

ahead efficiently. The excellent relationships

we have with our client, professional team

and contractors have, of course, been critical

to the success of the project.

Frank Africa has an experienced design

and construct team, especially in this

geographical area. “In the face of severe

challenges we have successfully provided

a lateral support design and constructed

solution that we have developed over the last

15 years and more in the Cape Town area,”

concluded Oldknow.

The CPUT Student Residence was

constructed within the group’s design

and construct model, opening up an

additional 295 beds, it brings relief to the institu-

tions high demand for student accommodation.

The design, by MLH Architects, offers maximum

occupancy with only double bedrooms and

shared amenities with the students’ comfort

and safety taking top priority. Biometric access

control was installed to control building access

with common areas strategically positioned at

the corners of the building – offering students

the best panoramic views of the Mother City

and Table Mountain.

Statistics released by the Department of

Higher Education and Training at the end of

2012 indicated a backlog of approximately

200 000 university beds, and since then the

depart-ments prime focus has been on student

housing funding.

“The NMC Construction group further

strengthens its portfolio in this sector with

the recent award of a new six storey student

housing development earmarked for students

of the Nelson Mandela Metropolitan University

(NMMU). Valued at R47,7-million the PE1 Devel-

opment for private developer, Campus Key,

it is located in Summerstrand – Port Elizabeth.

“In addition to these projects, we have

commenced with construction of the new

R40-million Heimat Student Residence for the

University of the Free State in January 2015, with

works on the R187-million Ndumo High School

in KwaZulu-Natal progressing well,” says Mike

van Coller, NMC Group procurement director.

Recently completed projects in this sector

include the R229-million OBZ Student Resi-

dence for the University of Cape Town and the

16 000 m² NMMU Student Living and Learning

Housing Development for the Nelson Mandela

Metropolitan University.

Summary of scope of works

• 21 000 m³ bulk earthworks

• 1 870 m² of lateral support consisting of excavation

in 1,5 m stages in depth

• Soldier piling comprising 147 No. 500 mm Ø CFA

piles using a B125 Casagrande drill rig

• Construction of the concrete capping beam.

• Trimming and construction of gunite arches via dry-

mixed, air-driven guniting

• Installation of ground anchors and temporary steel

walers at designed intervals

• Installation of temporary dewatering system and

sacrificial piling platform

• Construction of temporary access ramp for

foundation piling rig access at base level

• Installation of Franki pile 600 mm Ø foundation piles

using a Franki British crawler piling rig

The perched water table had to be

constantly managed to ensure that the

in situ soils would not become saturated.

EXPANDING INTO EDUCATION

NMC Construction Group

Established in 1983, the NMC Construc-

tion Group is a multi-disciplinary

construction group with a national

footprint and SADC presence. Currently

the organisation has offices in Cape

Town, Johannesburg, Durban, East

London, Port Elizabeth, Kathu,

Springbok and Windhoek.

The business growth is attributed

to the NMC Construction Group’s

strategic intent to expand its market

space to include civils infrastructure

and to diversify its building portfolio

to include commercial, retail, bulk

residential and institutional and social

services sectors.

The NMC Construction Group’s

civils and building divisions are ISO

accredited in the following three ISO

standards; ISO 9001, ISO 14001, OHASA

18001. These entities have a level 2 and

level 3 BBBEE rating and a CIDB GB9

and CE8 grading respectively.

>

The NMC Construction Group’s building division, has successfully

completed a new R51,4-million student residence for the Cape

Peninsula University of Technology (CPUT). Students are expected

to occupy the residence in the third semester of 2015.