Background Image
Previous Page  36 / 72 Next Page
Information
Show Menu
Previous Page 36 / 72 Next Page
Page Background

34

CONSTRUCTION WORLD

AUGUST

2015

PROJECTS AND CONTRACTS

>

Redefine Properties Limited,

the owner and developer of the

complex, set out to upgrade the

complex to an A-grade office

building by wrapping the envelope in high

performance architectural glazing, and adding

an additional 1 500 parking bays in the form

of a 13-storey parking structure between the

two towers, while keeping and upgrading the

public square.

Construction commenced in April 2013,

with the parking structure columns being

constructed in the existing basements, and the

project is due for completion in August 2015.

Aurecon was appointed as the structural

engineer of the project.

An interesting challenge on the project

was to maintain a column-free space in the

existing public square, with the top 10 levels of

the parking structure cantilevering 13 m over

this square for a distance of 55 m. To achieve

this, Aurecon conceived a 50 m span x 25 m

high A-frame Megatruss.

Dimensions of the Megatruss

The A-frame concrete truss encompasses an

area 55 m long x 25 m high. The main load

carrying members include a 600 mm wide x

2 750 mm deep bottom tension tie,

450 mm wide x 2 500 mm diagonal compres-

sion members and 450 mm x 1 800/1 500 mm

vertical hangers. The truss was temporarily

supported on 1 m square concrete columns

(approximately 20 m high) with precast

tapered column heads and packing plates.

How it works

The truss is designed to span 50 m clear,

carrying nine to ten suspended floors – it is

essentially a ‘mega’ transfer element, trans-

ferring the gravity load to the L-shaped shear

walls at the ends. It also plays a significant

role in the seismic resilience of the structure,

with ductile zones detailed within its critical

regions to absorb and dissipate energy during

strong ground motion excitation.

The A-frame form is a superbly rigid structure,

utilising the full depth of the front façade

(approx. 25 m). Long term deflections are

a critical design consideration and these

are controlled by utilising the stiffness of

the large concrete sections in compression

only – in other words, where tension would

exist in the final form, those members have

been prestressed so that the full, un-cracked

concrete area resists elongation stresses.

Why it is unique – and is it

unique to Africa?

The structure is unique in that it is an

entirely bespoke design, tailored to suit the

constraints of the site and the Cape Town City

Council requirement that the public square

remain as open (i.e. column-free) as possible.

In a way it is also unique to Africa in the

sense that concrete elements are largely

utilised to form the truss, whereas the more

conventional/classical methods in European

countries would be to employ mainly struc-

tural steel. In the African context, making use

of concrete in lieu of structural steel makes

sense in terms of employing more labour, and

improving cost-effectiveness.

What is especially unique is the fact that

an entirely separate, temporary concrete

structure was built (complete with piles) to

support the A-frame until the full frame was

completed, and then demolished afterwards.

This was required due to the large magnitude

of the temporary loads, which would overload

any conventional back-propping system. Once

the A-frame was completed, the tension ties

and hangers were prestressed (varying from

5 000 to 14 000 kN), and the bearing on the

temporary columns was released through

a phased downward-jacking process, using

INNOVATION

at Merriman Square

Merriman Square in Cape

Town’s Central Business

District consists of The

Towers, a 10 and 20-storey

building complex that was

built in the 1970s, with

an open public square

separating them.

Architect’s impression of the completed project.

Aurecon Revit model of the A-frame truss

resting on the temporary columns.

Megatruss bottom chord being jacked up, with shim plates separating; the total expected long term

deflection is 25 to 30 mm.