Background Image
Previous Page  42 / 72 Next Page
Information
Show Menu
Previous Page 42 / 72 Next Page
Page Background

40

CONSTRUCTION WORLD

AUGUST

2015

PROJECT PROFILE

ABOVE:

A 50 t crane will be used to place trees

in special concrete boxes in this external garden

area.

LEFT:

One of the signature siding walls

which required high quality concrete to achieve

the necessary finish.

Huge project

Bridge Park forms part of a larger precinct

development at Century City. Murray & Roberts

Western Cape’s success at this prestigious office

development resulted in it securing another

contract, Century City Square, which is domi-

nated by the iconic Apex Building, as well as

housing a conference centre, a hotel, a mixed

use building including offices, showrooms and

apartments as well as parking. It will feature a

canal system on two sides of the development

with pedestrian and vehicle bridges.

“It is a massive project, not only in terms

of the entire footprint, but also in terms of the

complexity of the individual elements. Bridge

Park, for example, is a single component of the

entire precinct. By itself it was a challenging

project that demanded attention to the finest

detail and strict project management practices.

This allowed us to not only meet, but exceed

the client’s requirements,” Jacobs says.

The project has recorded impressive statis-

tics: 17 500 m

3

of concrete was used, in addition

to 1 734 t of rebar and 6 500 m

2

of brickwork.

The plastering comprised 19 934 m

2

of screeds,

9 131 m

2

of internal work and 9 757 m

2

of

external work; 9 757 m

2

of Marmoran coating

was used, as well as 28 426 m

2

of paint.

Bridge Park demonstrates the capability

of Murray & Roberts Western Cape to meet

the complex challenges posed by such major

projects. A particular focus was the subse-

quent smooth transition to working at Century

City Square, without unnecessary duplica-

tion of infrastructure. “The site itself is quite

constrained, if you take the canal and road

system into account, in addition to the Bridge

Park office development itself.

“As we progressed with Bridge Park, and

later began to work on Century City Square

as well, the site area between the projects

had to be carefully managed for equipment

access and transportation of construction

materials. However, our major strength is our

project management capability. Our resources

and processes in this regard not only assisted

with Bridge Park, but allowed us to integrate

seamlessly with Century City Square,” Jacobs

explains.

He attributes the smooth progress at

Bridge Park to the co-operation of the entire

professional team, in conjunction with the

input of the client. “It has been a very tight

programme. We secured the Bridge Park

contract on a highly competitive tender basis.

It has been a fantastic achievement on the

part of the entire Murray & Roberts Western

Cape team. We also have an excellent team of

consultants that facilitated the process. At the

end of the day it is the total team effort that

sees a major project like Bridge Park through

from start to finish,” Jacobs says.

Murray & Roberts Western Cape has

clocked up over 500 000 manhours without a

single lost-time incident at Bridge Park to date,

testament to the safety culture fostered by the

Murray & Roberts Group’s STOP.THINK.ACT 24/7

programme. “We take health and safety very

seriously and are very proud of our achieve-

ment in this regard on this complex project

site,” Jacobs concludes.