Background Image
Previous Page  32 / 72 Next Page
Information
Show Menu
Previous Page 32 / 72 Next Page
Page Background

30

CONSTRUCTION WORLD

AUGUST

2015

PROJECTS AND CONTRACTS

The project

In the words of Franki senior contracts

manager Jim Oldknow: “Having carried

out numerous basements in the Claremont

area, we are able to anticipate the condi-

tions and create the most cost-effective

solutions. Because of this we are often the

recommended tenderers or we are requested

to negotiate the contract to the financial

budget, as was the case with the Citadel

contract,” he says.

Challenges

Oldknow adds that the type of basement

construction on this project posed a number

of challenges both in the general design and

in the design of the lateral support require-

ments. “The soils on this site consist of a 3 m

– 4 m layer of transported silty sand beneath

which is high-weathered decomposing

granite consisting of weak clay in the form of

kaolin. This extends to a considerable depth

of 20 m. A perched water table rests on top

of these kaolin clays and is visible within the

first 2 m from natural ground level.

“The basement, consisting of four levels,

is approximately 50 m x 50 m with a depth

of 12 m at the deepest wall height. One of

the major difficulties on this project was

the restricted access to the site with only

two access points for materials and plant in

and out and both exiting onto the very busy

Cavendish and Warwick roads in the Clare-

mont CBD. This was exacerbated by the small

footprint of the site combined with the depth

of the basement. All this severely limited our

ability to provide suitable access ramps for

the heavy plant,” says Oldknow.

“From a geotechnical perspective the

central challenge was that the very low

shear strength of the kaolin, in which ground

anchors had to be installed on this project,

has a limiting effect on the maximum

possible anchor loads. This, combined with

the disintegrating qualities of the kaolin,

when exposed to ground water, results in

nominal maximum anchor loads of 450 kN,”

he says.

It is well-known that lateral support

movements can be considerable in these

soils. And the perched water table certainly

didn’t make things any easier. This had to be

constantly managed to ensure that the in-situ

soils did not become saturated and make the

working platform inaccessible or unstable.

As the lateral support progressed the perched

water table was caught behind the gunite

arches and transported to excavation levels

by drains. This required constant de-watering

in order to prevent the disintegration of the

kaolin in slurry/clay. “Key to the success of

the project was the creation of a suitably

hard standing area and de-watering system

CHALLENGING

Cavendish project

Over the years Keller’s

Franki Africa (Franki)

has performed some

landmark geotechnical

work in Southern Africa

and beyond, providing

interesting, innovative

and often brilliant

solutions for a vast range

of challenging geological

conditions. Such

conditions contributed to

Franki being awarded the

Citadel Basement Parking

Project in Claremont,

Cape Town.

Quantity summary

• 1 870 m²of lateral support

• 147 No. 500 mm Ø Soldier piles

• Foundation Piling 210 No. 600mm

Ø Franki DCIS Piles

• 21 000m³ Bulk Earthworks

The four level basement measures

approximately 50 x 50 m with a depth

of 12 m at the deepest wall height.