Background Image
Previous Page  37 / 82 Next Page
Information
Show Menu
Previous Page 37 / 82 Next Page
Page Background

January 2015

MODERN MINING

35

PLATINUM

As a result of the Optimisa-

tion Plan, both the main

and ventilation shafts have

been shortened.

of mine. The net change in the project’s NPV is

a positive R2,1 billion to R6,5 billion, the main

contributors to this being the shorter timeframe

to full production and the lower nominal capi-

tal cost.

Prior to the recent Merensky Reef intersec-

tion, the previous major milestone passed

during 2014 was the cutting of the first sta-

tion/level on the ventilation shaft at a depth

of 680 m in May. When

Modern Mining

visited

the site at that point, the project was progress-

ing well with the rate of advance on the shafts

being targeted at 58 m per month, an objective

which has since been met.

The fact that the main and ventilation shafts

are now expected to be completed well ahead of

the original schedules is a considerable achieve-

ment for Wesizwe given that the shaft sinking

was at one stage running late as a result of the

delayed delivery of Eskom’s phase one 20 MVA

power supply to the site. However, an intense

focus on shaft sinking performance has helped

reverse the situation, as has the simple fact that

– as a result of changes implemented as part of

the Optimisation Study – the shafts are now

shorter (by 30 m in the case of the main shaft

and 50 m in the case of the ventilation shaft)

than originally designed. The shortening of the

shafts has been accommodated by the removal

of the large underground primary crusher cham-

ber originally planned and by bringing level

development onto on-reef horizons.

As part of the optimisation, a third shaft has

been added to BPM’s infrastructure. This will

be a 6 m diameter, 720 m deep shaft which will

give extra capacity for men and materials and

added ventilation capacity and current think-

ing is that it will be raise-bored. The new shaft

will only be needed towards the end of the

development phase, so it will probably only go

out to tender in late 2016.

Generally, BPM has experienced a good

safety record but this was marred in October

last year when a fatality was experienced dur-

ing shaft-sinking operations – the first on the

project. Ironically, the fatality occurred not long

after the site had celebrated reaching the mile-

stone of 500 000 fatality-free shifts.

The main shaft will have a hoisting capacity

of 255 kt/month of ore and 15 000 t/month of

waste. An initial 230 000 tonnes a month will

be mined from the Merensky Reef with the bal-

ance coming from the UG2. Ultimately, once

the Merensky reserves are depleted, the mine

will become an exclusively UG2 operation –

but this is not expected to occur until well into

the mine’s 30-year life.

The steel headgear of the main shaft, inci-

dentally, is noteworthy as being – at 87 m – one

of the tallest in the world. As has already been

widely reported, it received recognition in the

2014 Awards of the Southern African Institute

of Steel Construction, winning the Mining and

Industrial Category of the competition.

The structure consists of an A-frame

designed to resist horizontal, vertical and wind

loads. The top three levels of the A-frame form

the sheave decks with the upper level at 72 m

above the bank. There is a 14 m square centre

tower between the bank and the underside of

the sheave levels that accommodates six oper-

ating floors. A 30-ton capacity electric overhead

travelling (EOT) crane and its support structure

tops off the headgear. To achieve a quick and

safe completion of the steel erection, the main

contractor – Louwill Bakgoni JV – planned and

The net change

in the project’s

NPV is a positive

R2,1 billion to

R6,5 billion, the

main contributors

to this being the

shorter timeframe

to full production

and the lower

nominal capital

cost.