Background Image
Previous Page  45 / 82 Next Page
Information
Show Menu
Previous Page 45 / 82 Next Page
Page Background

January 2015

MODERN MINING

43

PLATINUM

T

he new mine, which according to

PTM, will exploit one of the last

large, near surface sections of the

Merensky Reef, will be an under-

ground operation. Proven and

probable reserves are estimated at 4,7 Moz 4E,

sufficient to support a mine life of in excess

of 20 years. Its neighbours include two other

developing mines, Bakubung and Styldrift,

which are owned by Wesizwe and RBPlat re-

spectively. While all three are underground

mines, Project 1 is accessed by declines while

Bakubung and Styldrift both have vertical

shaft systems.

PTM, which owns 82,9 % of the project, says

its investment in the new mine totalled US$343

million as of the end of November 2014 with

the peak funding requirement currently pro-

jected at US$502 million. According to the

company, its current cash position should be

sufficient to complete the mine build to initial

production.

With production nearing, Project 1’s manage-

ment team has been expanded. Key operational

roles that have been filled in recent months

include mine general manager, production

manager, equipment specialist, engineering

specialist, safety and environment manager and

a training superintendent.

Project 1 will have two distinct sections –

the North and South mines. As at the end of

the reporting period, over 7 600 m of access

development had been completed at the North

Mine and chairlift and conveyor construction

had begun. Development along the Merensky

Reef and the first underground raises had

been started and stockpiling of Merensky Reef

development material was underway, with

approximately 106 000 tonnes on surface as at

30 November.

At the South Mine, the boxcut is complete

WBJV Project 1

platinum

mine now 70 % complete

and, by the end of November, underground

mining had advanced the material decline for

approximately 949 m and the conveyor decline

for approximately 741 m. In total, over 2 206 m

of access development has been completed at

the South Mine.

As regards the processing plant, foundations

for major mill and concentrator components

have been completed and major mill compo-

nents delivered, including the mill shell. The

structural steel for the mill and flotation cir-

cuits has largely been completed.

In terms of Project 1’s power requirements,

a 10 MVA installation is in place with work

underway on an additional 10 MVA supply.

The full steady state requirement of the mine

is 40 MVA.

Current site construction, underground

development and management complements

total over 1 700 people, with approximately

Flotation circuit

construction at the

WBJV Project 1 site.

In its latest quarterly report (for the three months ended 30 November 2014), Platinum Group

Metals (PTM) says that it achieved a solid performance in 2014, with a good safety record,

at its Western Bushveld Joint Venture (WBJV) Project 1 platinummine, which reached 70 %

completion. Project 1, located on the Western Limb of the Bushveld Complex 35 km north-west

of Rustenburg, is due to enter production towards the end of this year. After a planned two-year

ramp-up, steady state production is scheduled at 275 000 ounces 4E a year.