Background Image
Previous Page  9 / 82 Next Page
Information
Show Menu
Previous Page 9 / 82 Next Page
Page Background

January 2015

MODERN MINING

7

MINING News

Weatherly International, whose shares

are quoted on London’s AIM, says its

Tschudi copper mining project in north-

ern Namibia is continuing to make good

progress. Comments company Chairman

John Bryant: “Tschudi is on track to com-

mence production in the second quarter of

this year. I must congratulate our UK and

Namibia teams on the progress they have

made.”

Tschudi is an open-pit mine which will

use heap leaching, solvent extraction and

electro-winning to produce high quality

copper cathodes. The mining reserve is

22,7 Mt at 0,86 % Cu, sufficient to support

an annual production of 17 000 t Cu over a

mine life of 11 years.

Mining at Tschudi has been underway

since July 2014 and ore continues to be

stockpiled in readiness for the crushing

plant to come on line.

On 19 December, 2 000 tonnes of

ore were run through the crushing and

agglomeration plant as a pre-commis-

sioning test with the plant achieving the

desired throughput rates. A second 2 500

tonnes was crushed and agglomerated on

2 January this year, this time focusing on

achieving the required agglomerate qual-

ity under full throughput. This resulted in

some minor modifications that have now

been completed.

Leach Panels One and Two are close to

completion (as of early January) and will

be ready to receive ore once the crushing

(Proprietary) Ltd, a Namibian empower-

ment group.

For 2015, Otjikoto is expected to pro-

duce between 140 000 and 150 000

ounces of gold at a cash operating cost of

approximately US$500 per ounce and all in

sustaining costs of approximately US$700

per ounce.

Once the plannedmill expansion is com-

pleted in the third quarter of 2015, B2Gold

expects annual gold production to increase

to approximately 200 000 ounces in 2016

and 2017. Otjikoto’s gold production will

also be enhanced by the development of

its Wolfshag zone, located adjacent to the

main Otjikoto pit. The company expects to

complete an updated indicated resource

study in the first quarter of 2015 along with

an updated mine plan by the end of 2015

which will evaluate open-pit and under-

ground mining at Wolfshag.

Namibia is not known as a significant

gold producer, with – for many years – only

one active gold mine, Navachab, in the

country. Navachab, which produced just

over 60 000 ounces of gold in 2013, was

originally owned by AngloGold Ashanti but

was acquired by QKR Corporation last year.

Otjikoto is a much bigger operation and

will result in Namibia’s total annual gold

production being substantially increased.

B2Gold is a Vancouver-based gold pro-

ducer with four mines around the world:

El Limon and La Libertad in Nicaragua,

the Masbate mine in the Philippines and,

of course, Otjikoto. The company is pro-

jecting to produce approximately 540 000

ounces of gold in 2015 and approximately

610 000 ounces of gold in 2017.

anticipated to be finalised in the first

quarter of 2015, to allow for the seam-

less development of the joint operation.

The equity component of the mine

financing was successfully raised as

part of the A$25,5 million capital rais-

ing undertaken with Ichor Coal and Coal

Development Holding during October

2014.

Universal Coal remains on track to

deliver this operation to the market dur-

ing 2015, having successfully developed

and commissioned the Kangala colliery

during the 2013/2014 year. The com-

bined operations will have an installed

capacity in excess of 6,25 Mt/a of pro-

cessing capacity, with expected ROM of

5 Mt/a.

Tschudi enters the final straight

Heap leach pad construction at Tschudi in November last year.

plant is in operation. The raw water and

raffinate ponds have been completed and

were filled with water over the Christmas

break.

On 17 December, the first acid road

tankers arrived from the Rössing uranium

mine and began unloading into the newly

commissioned acid storage tank, with

approximately 650 tonnes delivered.

Originally, acid was to be sourced from

the nearby Tsumeb smelter but construc-

tion of the smelter’s acid plant has been

delayed. As an interimmove,Weatherly has

signed a one-year contract with Rössing

Uranium to import acid through the port

ofWalvis Bay. Imported prices are currently

lower than those offered by the smelter

and, as a result, the contract (with Dundee

Precious Metals) is being renegotiated.

On 14 December, Nampower (the

Namibian power utility) signed off on the

high voltage installation, enabling the site

to switch to the main grid supply when

ready and replacing the temporary gener-

ating sets that have been used for much of

the commissioning work.

Recruitment of theWeatherly workforce

is complete and operators are currently

undergoing training under the supervision

of the specialist commissioning group,

PPM Global.

Commissioning of the SX-EW will com-

mence as soon as there are sufficient

stocks of pregnant leach solution available

at the required grade.