Previous Page  147 / 294 Next Page
Information
Show Menu
Previous Page 147 / 294 Next Page
Page Background

It was known at this meeting that the British com-

panies did not intend to apply to the Irish Bureau for

Green Cards, and thus P.M.P.A. were the only company

which would have to give security for cards. In March

P.M.P.A. confirmed that they would be a party to the

fundamental agreement, which was eventually dated

10th July 1970. The P.M.P.A. then petitioned the Court

to have the resolution of 9th March 1970 cancelled. It

was contended firstly that the agreement was invalid on

the ground that it attempts to regulate Green Cards in

a manner contrary to the fundamental agreement. This

fundamental agreement was not in force in March 1970

and cannot thus be invoked. On the other hand

P.M.P.A. cannot successfully invoke the agreement of

1953 as they were not parties to it. In the first place,

the resolution of 9th March 1970 was not

ultra vires

the company. However, the fact that the fundamental

agreement was only executed in July did not excuse the

Bureau from its obligation to give to each of the parties

to the agreement any Green Cards which they requested

without any condition as to security as long as they

were members. The requirement of a security of

£10,000 for each 1,000 Green Cards is clearly inconsis-

tent with the main purpose of the fundamental agree-

ment that it should be regarded as rescinded. It was

clear that P.M.P.A. had not accepted the resolution of

March 9th, or precluded themselves from objecting to it

subsequently by signing the fundamental agreement.

It was also contended by P.M.P.A. that the resolution

of March 9th was an oppressive exercise by the directors

of their powers and that the Court should accordingly

cancel it under Section 205 of the Companies Act, 1963.

The conduct or exercise of the powers complained of

under Section 205 must affect the person making the

complaint in his character as a member and not as a

creditor. A member of the Irish Bureau does not by

membership acquire the right to be supplied with Green

Cards because the articles of association do not confer

this. Therefore the claim under Section 205 fails.

Oppression can, however, be defined as harsh conduct

or depriving a person of rights to which he is entitled.

Green Cards are only valid for one year until the insur-

ance policy is renewed. As P.M.P.A. have 100,000

policy holders, the resolution of 9th March 1970 would

require them to deposit £100,000 per year, for an inde-

finite period. The relation of the securities in respect of

possible liabilities arising under cards issued up to ten

years before is so unreasonable and involves such a large

sum for security that it is oppressive. Nevertheless, given

all the circumstances of the case the directors acted

honestly when they passed the resolution in March and

also acted in what they believed to be the interests of

the Irish Bureau.

The petition was accordingly granted, and a declara-

tion was made that the resolution passed on 9th March

1970 in relation to the issue of green cards ceased to be

valid on 10th July 1970.

[Re Irish Visiting Motorists Bureau Ltd.; unreported;

Kenny J.; 27th January 1972.]

Con t r a c t:

Building contractors entitled to be paid

on a quantum meruit basis when no price is agreed

upon.

Plaintiffs, building contractors, claim £5,103 being

balance due by defendants for materials supplied and

work done to a house in Gorey from June to September

1969. Defendants (husband and wife) allege that the

£7,500 which they have paid plaintiffs fully discharges

their liability; but admit that a sum of £900 is due for

the installation of central heating. The defendants,

however, make a counterclaim in respect of:

(1) £3,600 damages for delay.

(2) £715 for alleged defects in workmanship and

materials.

The main dispute is as to the terms and construction

of the verbal contract.

The plaintiffs contend that it was a contract to sup-

ply certain materials and do certain work, and that no

fixed price or time for completion had been agreed

upon. The defendants contend that the contract was

to do the work and supply the materials at a definite

price, and that the work was to be definitely completed

by a certain date. The lady defendant, Mrs. Roche,

approached the architect, Smith, who was acting for

plaintiffs, in connection with a two bedroomed exten-

sion to her house late in 1968. A draft survey was

made. In May 1969 it was suggested that twenty-six

Germans would be visiting Gorey for ten weeks from

July 10th and that if accommodation could be extended

to include six new bedrooms, she could get a booking.

On May 23rd Mr. Smith was instructed to prepare

drawings, and on May 26th a discussion took place

between Mr. Smith and a director of the plaintiff

company, Mr. Campion, who took away the drawing.

The date for completion was mentioned as July 8th.

The plaintiff who had been aware of this, wrote to

Mr. Smith on June 10th stating that the extension

would not be completed in time, and suggested that

the plaintiff should make alternative arrangements

about the accommodation. Mr. Kilbride, the quantity

surveyor, having been asked by the plaintiff for an

approximate price for the extension, mentioned, after

calculations the figure of £9,800, to Mr. Smith; Mr.

Smith tried to suggest that the figure mentioned was

£8,900, and that he could name a target figure of

£7,500 to the defendant. On May 28th Mr. Smith

rang Mr. Kilbride, and told him to go ahead, provided

he kept as close to the target figure of £7,500 as

possible. The work then proceeded. The term "target

figure" according to the defendant meant that it could

not be scaled upwards, but only downwards The

plaintiffs contend that "target figure" simply meant an

approximate price which could be varied either way-

The Judge held that it did not mean that the final

cost was not to exceed this figure. Finally this work, on

a time and material basis, greatly exceeded the target

and came to £11,000. If no price is agreed upon, it i

s

clear that the contractor should be paid a reasonable

sum on a

quantum meruit

basis for materials supplied»

work done, and services rendered. As the construction

of the extension on a rates basis would have been

about £8,500 as against £11,000 on a time and material

basis Pringle J. felt bound to reduce the amount

clamed by a substantial amount. A reasonable figure

for the plaintiff was £11,200, and as £7,500 had

already been paid, they were entitled to judgment f°

r

£3,700 balance.

As regards damages for delay in completion, the

plaintiffs contended that, despite the tight schedule»

the defendant would not allow them to work on Sun-

days. Furthermore a German representative visited the

site on June 14th and was so dissatisfied with what h

c

saw that he subsequently cancelled the visit of the

German tourists After this, defendant decided to instil

central heating, and a contract was entered into -with

a

sub-contractor to have this done for £900; this mean

1

that the urgency for completion disappeared. In fa

ct

146