Table of Contents Table of Contents
Previous Page  28 / 76 Next Page
Information
Show Menu
Previous Page 28 / 76 Next Page
Page Background

TenneT is planning a trial run of underground

superconducting high voltage cable in the

Dutch electricity grid. The project will be a

first, as a section of superconducting cable

of this length (between 2km and 4km) has

not yet been installed anywhere else in the

world.

The 150kV cables currently in use require

a right of way of at least 12m wide to

dissipate the generated heat. HTSC (high

temperature superconducting) cables

require only a 3m strip because they

generate no heat, and no magnetic field.

Working with several leading institutes on

the project —Delft University of Technology,

University of Twente, the Institute for Science

and Sustainable Development, HAN

University of Applied Sciences, and Imtech

Marine – TenneT has yet to find a suitable

location for the test run.

Superconducting cables are expensive,

costing approximately three times as much

as a standard 110kV or 150kV cable, and

initially it will only be possible to use them in

sections of up to 4km. The superconducting

state in high temperature superconducting

cables is achieved by refrigeration to

-200°C using liquid nitrogen and this limits

the cable length.

In the first of two German auction rounds,

DONG Energy has won the right to build

three offshore wind projects in the German

North Sea. DONG Energy submitted six

projects in the bid and won with OWP West

(240MW), Borkum Riffgrund West 2 (240MW)

and Gode Wind 3 (110MW). The three

projects are planned to be commissioned

in 2024.

For two of the projects – OWP West and

Borkum Riffgrund West 2 – DONG Energy

made bids at €0 per MWh, meaning that

these projects will not receive a subsidy on

top of the wholesale electricity price. The

Gode Wind 3 project was awarded based

on a bid price of €60 per MWh.

HTSC on trial

Auction successes

wiredInUSA - May 2017

28