Background Image
Previous Page  29 / 64 Next Page
Information
Show Menu
Previous Page 29 / 64 Next Page
Page Background

27

CONSTRUCTION WORLD

MARCH

2015

sarily round, from which would hang the

viewing platform and hoisting structure. So,

introduce a Toblerone profile compression

ring at lower and upper levels of the roof.

Attach the upper parts of the columns to

the compression ring in a manner that would

allow them to rotate in plan, make them

also Toblerone in profile with curved upper

ends (like those shoulder parts). Make the

lower columns out of big tubes, whose final

length and shape of the ‘dog’s leg’, which

kink near their tops, and would be finalised

on site after erecting the roof (on tempo-

rary supports) based on the positions of the

bases now drilled and welded into position.

Excellent use of steel

The detailing and fabrication of a tubular

structure like this takes a special team.

Spiral Engineering, the steel contractors

on this project, is one of a few companies

with the skill and dedication to build such a

complicated structure.

Project team

• Developer:

The University of the

Witwatersrand School of Geosciences

• Architect:

Krynauw Nel Associates

• Structural engineer:

Peter Fellows

Consulting

• Quantity surveyor:

Crane QS

• Project manager:

Craig Harrison PM

• Main contractor:

Omni Struct Nkosi

• Steelwork contractor:

Spiral

Engineering

• Detailer:

KRU Detailing

• Cladding:

Cupric Tectonics

• Painter:

Mzekizeki Painters

The original brief:

• The structure must protect the fossil

bearing deposits from elements –

particularly rain and falling debris and

must prolong working hours on site for

the scientists.

• The structure must act first and foremost

as a platform for research.

• The structure must be able to

accommodate tourism, or group visits of

up to 48 people, but must separate these

visitors from the research activity.

• The structure must be able to lift rocks

weighing around one metric ton

PROJECT PROFILE – STEEL CONSTRUCTION

The proposed structure was to have no concrete

footings), and removable, should it ever be

required – leaving minimal traces. It was clear

that some steel structures would be the answer.

The accuracy of the detailing and the dimen-

sional accuracy of the fabrication was

tested during a trial assembly on temporary

supports (thus emulating the actual erection

procedure) at a local rugby ground.

Erection

To reach the site, one has to cover the 7,5 km

farm track road, which runs partly through

a river bed. Special trucks with limited

capacity were used on the farm. After four

unsuccessful tries, finally a 30 ton all-ter-

rain crane made it to site and had a long

enough radius and capacity to reach without

damaging the trees and the bush.

Once the roof structure was erected

on the temporary scaffolds and the upper

columns were hung, only then could the final

site-made dog’s leg kinks be done, leaving

the beetle standing on its own legs.

and move these rocks to a vehicle

loading point.

• The structure must not have a significant

foundation and be as close to free

standing as possible.

• The structure must not make contact

with the ground within the anticipated

10 year excavation goals. The structure

must be, due to the nature of the

environment, temporary as it will

almost certainly be there for many

decades it must be permanent in

nature (thus a temporary-permanent

structural design).

• Due to the sensitivity of the environment

the structure sits within, it must be

as near as possible ‘invisible’ within

the environment.

• Due to the importance of the fossils it

protects and the projected tourism and

VIP visitations, the structure must be

impressive when one is within it and

reflect the importance South Africa holds

for these World Heritage objects.

• The structure must tell in its architecture

the story of the site and the discoveries

made there.

• The structure must be fire and

animal resistant.

• The structure must be low maintenance.

• The structure must be flexible for

placement when on site.

• The structure must allow for expansion

of the excavation in the future.

• The structure must be, where possible,

manufactured in South Africa and use

environmentally friendly materials

where possible.