Background Image
Previous Page  40 / 64 Next Page
Information
Show Menu
Previous Page 40 / 64 Next Page
Page Background

38

CONSTRUCTION WORLD MARCH 2015

PROJECTS AND CONTRACTS

SANITECH

The wind farm is jointly owned by

Spain’s Acciona Energy and South

Africa’s Aveng Group and when

completed in 2015, will feed up

to 138 MW into the national grid daily. An

agreement between the JV and Eskom will

see ownership of the entire operation being

transferred to the utility giant after 20 years.

Precast towers

The towers are being manufactured by Cape

Town-based precast concrete producer and

Concrete Manufacturers Association NPC

(CMA) member, Concrete Units, in a joint

venture with another Spanish company,

Windtechnix. The latter has extensive experi-

ence in the manufacture of precast concrete

wind towers and is providing engineering

input. Once the project is completed some

16 500 m³ of concrete, 2 800 tons of rein-

forcing steel and 160 000 m² of shuttering

will have been used.

The on-site assembly of the towers and

manufacture and installation of the turbines

is being handled by Acciona Energy’s sister

company, Acciona Wind Power. Another

local company, civil engineering consul-

tancy, Concrete Growth, was appointed by

Acciona Wind Power as an external quality

auditing agency, responsible for the imple-

mentation of quality management in the

manufacturing process.

According to Concrete Units Cape Town

manager, Brian Cook, each completed

tower comprises five 20 m tapered concrete

sections, each section assembled from indi-

vidual precast concrete segments.

How it fits together

The base section, T1, comprises four

segments and is mounted on an in-situ

concrete foundation. T2 which is mounted

on T1, and T3, which is mounted on T2, are

also assembled using four precast concrete

segments each, whereas T4 is constructed

with three parts and T5 requires only two.

T5 sections are assembled at Gouda’s

storage yard where they are made ready

>

for supporting the turbines. Turbines

consists of the nacelle and hub which

weigh 140 tons, and three blades each

weighing 10 tons. Sections T1 – T4 are

assembled at the actual tower sites where

individual segments are lifted off the trucks

and then lowered vertically onto circular

concrete bases by a giant mobile crane. They

are then joined to matching segments using

‘bowtie’ connections.

This is achieved by inserting reinforcing

into hollow slots formed by the segments’

two opposing vertical channels. A proprie-

tary high-strength grout is then pumped into

the joint to create a permanent seal.

The 20 m sections are attached to each

other in a horizontal plane using male

starter bars at the bottom end and female

ducting at the top end and these joints are

sealed with grout. The flawless execution

of this process requires extremely accurate

casting and very tight tolerances.

Durability

The Gouda towers have been designed to

bend with the wind and can move up to

700 mm at the top of T5 during strong winds.

This flexibility is facilitated by the use of

steel reinforcing inside the tower walls.

However, this lateral movement is counter-

balanced by the installation of six 90 mm

steel cables, which attach the inner wall of

T5 to the concrete base and provide addi-

tional strength to the overall structure. Once

GOUDA

WIND

FARM

Forty six precast concrete towers are being deployed for the

construction of one of South Africa’s largest wind farms to date,

situated on farmland in the Gouda district of the Western Cape.

The towers stand at 100 m and support wind-powered turbines,

each with a maximum generating capacity of 3 MW.