Background Image
Previous Page  41 / 64 Next Page
Information
Show Menu
Previous Page 41 / 64 Next Page
Page Background

39

CONSTRUCTION WORLD

MARCH

2015

PROJECTS AND CONTRACTS

Renewable energy

Moreover, wind power forms part of the

Government’s renewable energy strategy

which was formulated by the Departments

of Energy and of Trade and Industry in 2011.

The CSIR was tasked with researching its job

creation and economic development poten-

tial, and it was on the basis of the CSIR’s

report that the DTI increased the local-con-

tent wind-farm requirement for Round Three

of its Renewable Energy Programme, of

which Gouda forms a part.

Alternative energy is scheduled to add

9 000 MW (equivalent to two coal-fired

power stations) by 2030, and it seems a

safe bet that precast concrete towers will

play a major role in rounds four and five of

the programme.

This article was first published in

Precast

installed they are post-tensioned by Acciona

Wind Power’s engineers.

The segments, 782 in all, are being cast

at Concrete Units’ factory using five moulds

which were shipped to South Africa from

Poland and Brazil by Acciona Wind Power.

Each mould section is two metres long and

the sections were attached to each other

using precision-based laser technology.

Moreover, to ensure the accurate layout of

the steel reinforcing, Concrete Units is using

special reinforcing jigs.

Casting

A maximum of five segments are cast daily.

Various types of inserts and sockets are cast

into specific positions to locate the mechan-

ical (ladders, lifts and landings) and elec-

trical equipment (cable trays etc) required

inside the towers. Spaces for doors are cast

into every fourth T1 segment. Mould strip-

ping takes place either late into the night

shift or first thing every morning by which

time the segments have reached a compres-

sive strength of 25MPa.

After three days the moulds are given

a light post-tensioning prior to being

transported to Gouda on extra heavy-

duty low-bed trucks. Segment T1 which is

5,5mwide and T2, which spans 4,8m, require

police escorts. The smaller segments, using

normal escourts, are generally shipped first

which then allows the trucks to return for a

second load.

Innovative products

Santie Gouws, managing director of

Concrete Growth, says that in terms of

concrete manufacture, the Gouda Wind

Farm project is cutting edge.

“For example, the tower segments were

designed according to Euopean as opposed

to SANS codes. This allows us to design up

to 115 MPa cube strength rather than the

60MPa which forms part of the SANS struc-

tural concrete code. The Gouda towers are

being manufactured to 75MPa which is the

strength required to handle the loading of

the turbines and the wind. This high char-

acteristic strength has allowed Acciona’s

engineers to opt for lighter concrete sections

which add a further eco-friendly dimension

to the project through lower material usage

and transport costs.

“Secondly, the towers are being manu-

factured with self-compacting concrete

(SCC). SCC is comparatively new to this

country and besides being the largest

wind farm to date, Gouda is also the coun-

try’s largest SCC project thus far. In fact it

is using approximately half the amount of

concrete used for the precast segments of

the Gautrain project.

“Without SCC the project would have

beenmuchmore complex, involving external

vibration and more expensive moulds.

“The SCC is being supplied by Megamix,

which has a batching plant close to Concrete

Units. The SCC mix is one of the critical

components of the whole manufacturing

process and one member of the Concrete

Growth team is permanently based at

Megamix to monitor the batching process.

Rainy weather can affect the mix because

the amount of water used is critical. Even a

slight water overdose can cause segregation

and a loss of strength. We have a system in

place and have had very few problems with

the mixes. Needless to say the slump flow

of every batch is tested at Concrete Units

before being pumped into the moulds.”

Gouws added that turbine towers gener-

ally amounts to approximately 15 to 20%

of a wind farm’s capital cost, a figure which

does not include the foundations.

In most instances, the higher one

goes, the better the wind, and for

heights above 80 m, concrete towers tends

to be less expensive than imported steel

towers, thus impacting on the cost of the

electricity generated positively.

To date, most wind turbines in South

Africa have been mounted on steel towers,

– which have the disadvantage of being

imported and a comparatively low local

labour and job-creation componnent.’

By contrast, concrete wind towers come

with high local-content inputs and by default

carry a much higher job generating capacity.

For example, over 95% of the raw materials

for Gouda’s concrete towers including the

reinforcing steel were sourced locally.