Table of Contents Table of Contents
Previous Page  21 / 46 Next Page
Information
Show Menu
Previous Page 21 / 46 Next Page
Page Background

the other topless crane with SA French.

A month after we had placed that order,

SA French came to us with the opportunity

to purchase the Potain MCT85F5 at a very

good price,” says Simmonds. “It was one

of those once-in-a-lifetime deals.”

Space challenges

From a coordination planning point of view,

the contractor faces major constraints with

the footprint of the building in relation to the

available laydown area. “So, material handling

and delivery is quite a headache,” says

Simmonds. “It all comes down to planning and

we have since overcome that with the arrival

of our MCT85F5 topless crane.”

“Getting materials vertically in a timeous

manner to all the various floors is of essence

to the workflow processes on site. We have

now introduced the second crane which is

purely for wet trades, such as brickwork,”

says Simmonds, adding that from a critical

path point of view, a total of 3,5 million

bricks have to go up to the various floor

levels. “From a supply point of view, as the

main contractor we have to provide our sub-

contractors with sufficient material every

day to meet the production timeline, hence

the arrival of the second crane on site.”

“The reason Probuild opted for a flat top

tower crane on this site is because of the

limited available space between the jib of

the existing Potain MD310B tower crane

and the top of the building,” says Louw

Smit, sales manager at SA French.

Crane establishment and disestablish-

ment generally contributes heavily on the

cost of the contract, and this is one of the

key issues that the flat top design of the

MCT85F5 addresses. One of the crane’s

key features is that it offers the luxury to

erect or dismantle it in 5 and 10 m piec-

es; the full jib doesn’t need to be lifted

as one piece.

Capital Equipment News

witnessed the erection of the Potain

MCT85F5 at Probuild’s building site in

Sandton, which was a unique experience

in the sense that it steered clear of the nor-

mal erecting standards of a tower crane.

The existing Potain MD310B tower crane

on site was used to erect the new MCT85F5

tower crane. It is most unusual to erect a

tower crane in this manner as it is usually

assembled along with a mobile crane. This

saved a lot of time and space constraints to

deploy a mobile crane. Quentin van Breda,

managing director of SA French, says the

unique erection method circumvented the

need for the nearby road to be cordoned

off to traffic. “Using a mobile crane would

have called for a partial, probably one-

• Overall height reduced with the crane having no top tower (topless crane)

• The design allows it to overfly other cranes on congested sites

• Jib can be erected/dismantled in 5 and 10 m pieces; the full jib does not have to be

lifted as one piece

• All the components of the crane can be containerised in standard containers for

easy shipping and transporting from site to site

• Comes with a 40LVF13 hoist winch reaching lift speeds of up to 81,5 m per minute

with a new power control function

• The winch can be adjusted to power sources using either 50 Hz or 60 Hz, protecting

components and simplifying set up

• New power control function allows the crane to work on job sites where power

supply is limited

KEY FEATURES/BENEFITS OF THE POTAIN MCT85F5

JOBSITE REPORT

The manual

turning of the

slewing turret

facilitates lifting

the counter jib and

having the slew

turret in the correct

position.

CAPITAL EQUIPMENT NEWS

DECEMBER 2016

17