237 Units including 3 Commercial Units,

3 Retail Units and 2 Restaurants

GENERAL SCHEDULE

Contributed by all units in accordance with their

units of entitlement

Bundled Disbursements

-

Bank Charges, Bas Lodgement, IT Charges, Storage,

Printing, Copying, Postage & Stationary, Tax

Lodgement and Management Fees as per current

agency agreement

Sinking Fund Forecast

-

Allowance to obtain professional sinking fund forecast.

Estimate based on scale of fees provided by QIA

Group @ $14.44 per lot.

Trade Waste

-

Nominal amount to cover the cost of extraordinary

rubbish removal, i.e. boxes left due to residents

moving in. Note that residents and commercial are

responsible to remove their own surplus non

household waste however it is expected that there will

be instances where non household waste is simply

dumped on common property and will require

removal. An allowance has been made for additional

pick-ups in the initial 4-6 weeks. Excess budget in this

category allows for the cost of extraordinary rubbish

collection by the cleaners and/or caretaker

Telephone

-

Allowance for rental of telephone lines required for

Fire Indicator Panel and 8 lifts charged approx $450

per line.

Cleaning

-

Allowance based on our general understanding of the

building with reference to other similar buildings in our

portfolio

Electricity

-

Expenses relating to the cost of communal power for

common area lighting and mechanical equipment @

$220 per unit. Plus an allowance for operating the

Lifts and other electrical motors such as pumps/roller

doors @ $12800. Expenses relate only to B1, B2,

Ground Floor and residential common areas.

Gas

-

Consumption for building hot water plant metered

separately by each residential and commercial/retail

tenant. Therefore no allowance has been made for

this budget

Insurance Building & Stamp Duty

-

Allowance based on our general understanding of the

building with reference to other similar buildings in our

portfolio

Fire Protection

-

Sprinklers only installed in B2, B1 and Ground Floor.

Allowance for service contract for fire systems of

mixed commercial/retail & 2 levels of car parks (for

residential units). Assumes that 12 months service is

provided from the date of completion.