Background Image
Previous Page  30 / 92 Next Page
Information
Show Menu
Previous Page 30 / 92 Next Page
Page Background

28

CONSTRUCTION WORLD

OCTOBER

2015

The mall was built by one of the

country’s leading rural retail

centre development specialists,

McCormick Property Develop-

ment, a company with a strong focus on the

emerging markets of South Africa. Engi-

neered Interlock Solutions (EIS) in conjunc-

tion with TMV Consulting Engineers designed

the geosynthetic reinforced concrete block

retaining walls. The walls were built by EIS in

close collaboration with the main earthworks

contractor, Joubert en Seuns.

EIS owner, Manie Troskie, says that EIS

won the retaining wall tender on the basis of

an alternative and more cost-effective design

PROJECTS AND CONTRACTS

>

which also offered better functionality.

“There are substantial quantities of

sub-surface water on this site and our design

had to make provision for extensive drainage.

In fact there were some embankment

sections where one could actually see water

oozing from the ground.

“Three walls were open-face designs and

were built with Aveng Infraset’s Terrace Blok®

TB 490 and TB 300 retaining wall blocks.

The other two walls were closed-face and

built with the Infrablok™ 350.”

The largest wall, some 200 m long,

was built in an open-face configuration

at an angle of 70˚. It was constructed on

the perimeter of the property to reinforce

an embankment which rose to 12 m at its

highest point from a service road below.

“We only had five to six metres to work

with on this wall and the installation of

extensive sub-surface drainage was required

before construction of the wall could begin.

Sub-soil drains were installed on top of the

foundations three-to-four blocks below

kerb level. Fin drains , wrapped in A2 bidem

which go right back to the cut face, were laid

to trap water at the top, sides and bottom of

the embankment.

“We also installed 250 mm Kaytech wick

drains which were wrapped with bidem. And

in areas with the heaviest water flows we

positioned 100 mm slotted pipes covered

with stone and Geomesh geotextile to trap

the water at the cut face. All ground water

drains into a pipe at the bottom of the wall

which runs parallel to the foundation and

feeds into the stormwater drainage system.

“The foundation of the perimeter wall

was steel reinforced. One metre wide, it

varied between 450 mm and 300 mm in depth

depending on the height of the wall.

STABILISING

BUILDING

platforms in Mpumalanga

Five geosynthetic reinforced retaining walls using precast

concrete retaining blocks manufactured by Aveng Infraset

have played a crucial role in creating stable terraces for

the construction of Emoyeni Mall, a recently completed

shopping centre situated on the R538 between Nelspruit

and Hazyview in Mpumalanga.

The 200 m perimeter wall at its highest point of 12 m.

The 200 m perimeter wall built with Aveng Infraset’s TB 490 and

TB 300 concrete retaining blocks.