Background Image
Previous Page  24 / 64 Next Page
Information
Show Menu
Previous Page 24 / 64 Next Page
Page Background

GOLD

22

MODERN MINING

July 2015

D

esigned as a hybrid gravity/

CIL and heap leach operation,

the Namoya mine poured its

first gold in Q4 2014. The prop-

erty lies at the southern end of

the Twangiza-Namoya gold belt in Maniema

Province, 225 km south-west of Bukavu, and

consists of one PE (Exploitation Permit) cover-

ing an area of 174 km

2

. Alluvial gold was first

discovered in the area in 1930 and was mined

between 1931 and 1947. Primary gold was

also discovered during this period and under-

ground mining on the Filon ‘B’ deposit began

in 1947. Formal mining ceased in the 1960s,

only recommencing with Banro’s development

of the present mine.

During wet commissioning of the process

plant last year, it became apparent that the effi-

ciency of the CIL circuit was being hampered

by the quantity of fines content in the ore, as

it exceeded the design capacity. The company

determined that the best solution to the problem

was to acquire an agglomeration drum to run the

mine as an agglomerated heap leach operation

while pursuing options to best utilise the CIL

plant to process the fines material. An agglom-

eration drumwas procured in the fourth quarter

of 2014 and installed in January this year.

In its quarterly report, Banro says that – as

previously reported – a delay in financing

resulted in a need to modify the mine plan to

allow for the pre-stripping of the Kakula reserve

pit. This modification impacted ore availabil-

ity early in the second quarter as the mine fleet

focused on waste removal in order to allow for

increased access to mining faces when the first

additions to the mobile fleet were commissioned

in late May. This contributed to a decrease in the

stacking level in April to 57 211 tonnes, which

subsequently increased to 130 974 tonnes in

May and 142 082 tonnes in June.

The significant decrease in stacking levels

fromMarch’s 103 163 tonnes to the much lower

April figure was also driven by the adverse

impact of unseasonably high rains which inter-

rupted supply routes and the ability to deliver

procured materials and supplies.

The availability of ore from mining activi-

ties and the available medium grade stockpile

material resulted in the stacking of ore with an

average grade of 1,52 g/t Au.

According to Banro, Namoya management is

Namoya

continues ramp-up

to

commercial

production

The processing plant at the

Namoya site.

Reporting on its activities in the second quarter, Canada’s

Banro Corporation says that its new Namoya gold mine

in the DRC continued to ramp up toward commercial

production levels, achieving stacking levels greater than

140 000 tonnes of agglomerated ore in June.