Previous Page  35 / 56 Next Page
Information
Show Menu
Previous Page 35 / 56 Next Page
Page Background

33

CONSTRUCTION WORLD

NOVEMBER

2016

Mining and industrial category winner

Husab Uranium stockpile cover & ancillary structures

The Husab Uranium Stockpile Cover & Ancillary Structures entailed the

detailing, fabrication, corrosive protection, delivery and installation of two

thousand six hundred tons of steelwork, as well as twenty-one thousand

square metres of IBR sheeting. The project duration including on and offsite

activities was fourteen months with the site duration being eleven months.

There were a number of interesting challenges to overcome, i.e. short

lead times, high specifications required by client, galvanizing of trusses,

for the logistical challenges due to cross border distances, lifting and

jacking in the 140 ton gantries and sheeting the building on forty-five

degree slopes. We pioneered some ideas at each phase to overcome the

challenges and ultimately bring the project home safely and in time.

Some highlights were:

• The logistical concern of delivering this volume of steel and sheeting

was overcome by partnering with a local transported and dedicated

trucking supplemented our in-house fleet.

• The development of the idea and plan to strand jack the gantries

(50-meter span and 140 tons) into place forty meters above ground

level, as opposed to using the traditional method of cranes, allowing

for this part of the project work to be done faster and safer, ultimately

saving the project time and the client monies.

• The development of sheeting gondola platforms, which supported a

four-man team, tools and materials. These working platforms allowed

for the sheeting installation crews to achieve around one thousand

two square metres of sheeting installation per day. The safety risk of

working on the steep slope was totally eliminated and went a long way

in ensuring that Union Steel achieved another incident free project.

• Preassembly of truss box section allowed for the site crews to lift into

place bigger sections of steelwork, minimising works being carried out

in the air, again target our approach to ensuring that our focus on all

projects is safety first, and driven with this mind-set.

Tubular category winner

Siesa Ramabodu Stadium

Scooping the award for best Tubular Steel structure was Siesa Ramabodu

Stadium in Bloemfontein. Home to Bloemfontein Celtic, the Stadium

was renovated to better serve the community by increasing its capacity,

comfort and quality as a sporting venue.

When interviewed regarding this project, the first aspect architect

Aadil Bham commented on was the professional and excellent manner in

which the team collaborated while executing this project. “All contrac-

tors and subcontractors really came together well to give us a good

final product.” says Bham. The project came about from a collaboration

between the Mangaung Municipality and the Freestate Department

of Sports, Arts, Culture and Recreation, and the Department of Public

Works. They identified this site as a priority for development within the

municipality and developed a wishlist in terms of what they wanted to

achieve. Their main priority was the upliftment of the sports offering from

this facility, bringing it to a contemporary standard. They also wanted

to create a facility that provided a quality experience to the community,

with soccer being such a loved sport in the area.

The structural frame of Seisa Ramabodu Stadium consists of main

raker beams, frames or columns which are founded on solid rock, with

seating panels and a box gutter frame bolted to a structure cast into the

concrete, carrying a cantilevered roof. The cantilevered roof spans about

30 m and consists of triangular trusses, constructed from circular hollow

sections. The trusses vary from 2 m at the back to 500 mm at the nose

cone, with a curved bottom member. It has IPE profile purlins that span

9 m (more or less the span of the raker beams) with curved cladding rails

fixed to the back of the concrete frames, which carry the circular purlins

that support the curved cladding.

The main challenge was casting in the structure that carries the

gutter boxes at the back. This resulted in variable items, and the need to

align trusses in order to create an even visual line, which contributes to

the aesthetic of the stadium. Between the engineer, contractor and archi-

tect a three member connection was designed to solve this challenge. All

aspects were surveyed, and each section had its own cleat made to align

the trusses and achieve an even visual alignment.

ON