Previous Page  38 / 56 Next Page
Information
Show Menu
Previous Page 38 / 56 Next Page
Page Background

PROJECT PROFILE

he event culminated in the announce-

ment of the overall winner for 2016,

the Eastgate Phase II Redevelopment,

submitted by Tass Engineering –

Steelwork Contractors and project

team members. In addition to being the overall

winner, this project also won the Commercial Archi-

tectural Category.

The Eastgate Phase II Redevelopment encom-

passes a number of new structures to give the centre

a major facelift. The primary change is the relocation

of the lower level cinema complex onto a section of

the roof-level car park, enabling more retail space at

the lower level plus incorporating substantial addi-

tional retail space within the new cinema complex

at roof level.

When asked about Eastgate Redevelopment

Phase II project, Spencer Erling, retired SAISC Director

EASTGATE PHASE II

redevelopment wins 2016 Steel Awards

The highlight of the structural

steel industry calendar, the

35

th

Annual Steel Awards

hosted by the Southern African

Institute of Steel Construction

in partnership with BSi Steel,

took place on 15 September

2016 in Johannesburg, Cape

Town and KwaZulu-Natal

concurrently. Attended by

over 1 000 people the event

showcased projects completed

in the previous year that

demonstrated excellence in

the use of structural steel.

and seasoned Steel Awards judge convener remarked:

“I’ve sent students there. I’ve seen the drawings. I just

think that what they’ve achieved in a working shop-

ping centre, that’s absolutely changed the mall totally,

is really a fantastic piece of engineering work.”

What makes this entry special?

What is special about this project goes hand in hand

with why steelwork was chosen as the main structural

component in its design. Building a major 5 000 m

2

structure such as this one on a suspended concrete

carpark slab over two levels of retail space and keeping

the entire shopping centre operational in the process

is no mean feat both from a design and a construction

point of view.

Underpinning of the foundations was undertaken

by mining under the existing lower level suspended

slabs firstly by excavating using remote controlled

Bobcats with their hoods cut off and then installing

mini precast piles.

Special consideration had to be given to access to

the workface for the installation of most of the steel-

work. The loading limitation on the rooftop carpark

slab was only 2 kPa with the maximum vehicle weight

limited to 5 000 kg.

The tower crane that was installed by the main

contractor on the site covered only 60% of the rooftop

cinema complex area and had limited load capacity

at radius.

A number of the internal structures were designed

with plate web girders spanning in excess of fifteen

metres which had to be manhandled into position and

hoisted by scaffold tower and chain blocks.

Loads of up to 3,5 ton and lengths of over 18

metres had to be trolleyed/man handled through and

around the cinema structure to then be hoisted to

final level by building high scaffold towers over them

and pulling them up with suitable capacity chain

blocks. an extremely time consuming and expensive

means of erection.

Connection design, particularly between the

numerous beams throughout the lower levels of the

cinema complex and all the Bond-Dek slab support

beams was a major cost saving item from a fabrication

36

CONSTRUCTION WORLD

NOVEMBER

2016