Background Image
Previous Page  29 / 56 Next Page
Information
Show Menu
Previous Page 29 / 56 Next Page
Page Background

27

CONSTRUCTION WORLD

FEBRUARY

2015

PROJECTS AND CONTRACTS

which amounted to about 123 840 m

3

of the 144 000 m

3

concrete, which

would otherwise have been disposed of at landfill sites. The quantity

that was not recycled came from structural concrete with a high level of

rebarred material. However, the rebar was recovered for off-site scrap

metal processing.

The old pavement was crushed to a G5 material specification and

reused as base and sub-base quality material. Apart from the posi-

tive environmental benefit of reusing the old pavement, the use of a

great deal of virgin aggregate was prevented. It is estimated that about

R14-million would otherwise have had to be spent on the procurement

of new aggregate and on transport.

Placing geopolymer concrete is very similar to placing Portland

cement, meaning no additional training for workers or extra equip-

ment. In addition, recycled materials such as slag and fly ash can be

used to make geopolymer concrete, thereby reducing the carbon foot-

print of the material by 80% to 90%.

Murray & Roberts Infrastructure achieved 51 MPa in 28 days, with

compressive strengths up to 80 MPa at six months. Fifty MPa is equiv-

alent to the pressure exerted by the weight of 10 pockets of cement

concentrated on the point of a single finger. The carbon footprint of a

cubic metre of cement is 350 kg to 400 kg of carbon dioxide equivalent

per cubic metre, and 100 kg/m

3

for geo-polymer concrete. This means

geopolymer concrete reduces greenhouse gas emissions by 60% to 70%.

Specific deconstruction processes

Deconstruction processes were as specific as the construction process.

The demolition of the existing infrastructure and feeding of this

resource as a material stream into the crushing areas and reprocessed

stockpiles meant a clear understanding of the quantities scheduled

for the foundations upstream. Planners and engineers thus needed to

understand the rates of the demolition, earthworks and processing of

the G5 to ensure that none of these processes entailed any delay.

Environmental impact

The resource-intensive traditional way of making cement has seen

the industry rank among the top environmental offenders, leading to

increased calls for more sustainable solutions.

The concrete used on this project achieved a 63% to 70% replacement

of raw milled clinker with siliceous PFA, almost double the maximum

specified limit on most construction projects. Using this quantity of

PFA alters the concrete hydrate formed in such a way as to increase the

durability/service life of the elements.

In terms of concrete technology, the reliance on coal fired power

stations for the majority of electricity in South Africa in addition to the

large metal resources, mean that large quantities of PFA and slag mate-

rials are readily available. The efficient uptake of such waste by-prod-

ucts can assist in economic growth by slashing the cost of construction

and increasing the durability of the structures being built.

From a client perspective Transnet, which operates multiple sites

countrywide, can incorporate the possibility of the reuse of existing

infrastructure in future refurbishments, in order to produce new prod-

ucts of high quality and durability that are also environmentally sound.

Murray & Roberts Infrastructure, in conjunction with Transnet, can

therefore reference this project as a benchmark case study.

Health and safety

Murray & Roberts’ values of safety, integrity and accountability as well

as the group’s STOP.THINK.ACT 24/7 zero harm culture is embedded

in the Environmental Framework, which is divided into four environ-

mental programmes, forming part of the larger Integrated Management

System (IMS):

• Integrated waste management

• Emissions and pollutants minimisation in construction

• Sustainable material and resource management

• Energy efficiency through mass balancing

The Murray & Roberts’ Exco has endorsed the SHEQ policy and Environ-

mental Framework and requires performance reporting. Significantly,

as at the end of June 2014 the contract had been running LTI free

for 12 months.

Project information

• Project start date: September 2012

• Project end date: October 2014

• Client: Transnet Freight Rail

• Main contractor: Murray & Roberts Infrastructure

• Principal agent: Murray & Roberts Infrastructure

• Project manager: Transnet Capital Projects

• Consulting engineer: Transnet Capital Projects

• Project value: R230-million