Previous Page  39 / 84 Next Page
Information
Show Menu
Previous Page 39 / 84 Next Page
Page Background

Figure 1. Data center monthly-amortized costs (source: James Hamilton’s blog)

industry faces pressure to scale

data centers, one of the most

constrained resources is power. It

is often the case that the power

capacity of existing data centers is

exhausted well before they run out

of storage or processing capacity.

The two main factors of this power

capacity limitation have been the

need to provide supply redundancy

and the way power is partitioned

within data centers, both of which

take up significant space but more

importantly leaving untapped power

sources idle. And this is despite the

fact that current server designs

are far more power efficient than

previous generations and have

significantly lower idle power

consumption.

Providing additional power capacity

within a data center is also time

consuming and expensive even

assuming that the local utility can

supply the additional load, which

IDC forecasts could double from

48GW in 2015 to 96GW by 2021 for

a typical data center. From a capital

expenditure standpoint, as shown

in figure 1, the power and cooling

infrastructure cost of a data center

is second only to the cost of its

servers.

The nature of Cloud services also

means that demand can fluctuate

dramatically with a significant

difference between the peak and

average power consumed by a

server rack. Consequently, providing

enough power to meet peak-load

requirements will clearly result in

underutilization of the installed

power capacity at other times. Also,

lightly loaded power supplies will

always be less efficient than those

operating under full-load conditions.

Clearly any measure that can even

out power loading and free up

surplus supply capacity has to be

welcome in enabling data center

operators to service additional

customer demand without having to

install extra power capacity.

With

regard

to

efficiency

considerations,

servers

and

server racks use distributed

power architectures where the

conversion of power from ac to dc

is undertaken at various levels. For

example, a rack may be powered

by a front-end ac-dc supply that

provides an initial 48 Vdc power

rail. Then, at the individual server

or board level, an intermediate

bus converter (IBC) would typically

drop this down to 12 Vdc leaving

the final conversion, to the lower

voltages required by CPUs and other

devices, to the actual point-of-load

(POL). This distribution of power at

higher voltages helps efficiency by

minimizing down-conversion losses

and also avoiding the resistive

power losses in cables and circuit

board traces, which are proportional

New-Tech Magazine Europe l 39