Background Image
Table of Contents Table of Contents
Previous Page  28 / 48 Next Page
Information
Show Menu
Previous Page 28 / 48 Next Page
Page Background

26

CONSTRUCTION WORLD

JANUARY

2015

PROJECTS AND CONTRACTS

The 148-room hotel forms part of

the Newtown Junction mixed-use

development, the biggest multi-

use development in the Johan-

nesburg CBD since the construction of the

Carlton Centre in the 1970s. The 8 000 m

2

hotel is being built by Archstone Construc-

tion of Pretoria for the developers, Atterbury

Property Developments.

Ignatius Maas, Gauteng Piling site man-

ager for the project on the corner of Miriam

Makeba and Carr streets (adjacent to the

Market Theatre), says the contract called

for the provision of 64 piles with an average

depth of 10 metres for the seven-storey hotel

scheduled to open next year.

“The piling contract provided some

unusual challenges and requirements. In the

Gauteng Piling providing the foundations for the new City Lodge Hotel in Newtown Junction.

CAPPED

PILING

for Newtown hotel

Gauteng Piling recently

provided the foundation piles

for a new City Lodge Hotel

being built in Newtown.

first place, we had to contend with excep-

tionally limited access, particularly at the

start of the contract, caused by building

operations on other encroaching facilities

that form part of Newtown Junction.

“Then we had to address redundant

sewer and stormwater services, for which

the concrete pipes were sandwiched

between concrete slabs about 250 mm

thick. These services required rectangular

concrete capping beams, joining sets of two

piles which were installed to straddle the

existing services where we could not drill

through them,” Maas explains.

Capping beams for piles aim at trans-

ferring loads from closely spaced columns

or walls into a row of piles. To install pile

capping, pile heads are stripped to expose

the steel reinforcement to be projected into

the pile cap. Steel reinforcement is then

placed at the desired location and a large

concrete block is formed to distribute loads

over the capped piles.

Gauteng Piling employed two rigs for the

City Lodge piling: a Williams LDH digger and

Soilmec RTAS which can drill into rock of 4 to

5 MPa. A third Williams rig was on standby.

Since the arrival of its first piling

machine in Johannesburg in July 1996,

Gauteng Piling has developed into one of the

foremost piling contractors in South Africa.

The company has to date completed over

1 500 projects and its current fleet consists

of 20 auger machines, two cranes, two bore

rigs, six Grundo hammers, and two lateral

support machines.

The Newton Junction was familiar terri-

tory for Gauteng Piling as the company had a

few months prior to the City Lodge contract,

provided the piling for extensions to the

Market Theatre complex.

Under the leadership of Hennie Bester,

past president of Master Builders Associ-

ation North, Gauteng Piling also provided

more than 500 piles for the construction of

southern African’s largest single-phase retail

centre, Mall of Africa.

Other recent contracts handled by

Gauteng Piling include the piling for the

large-scaled Value Logistics warehouse

in Kempton Park, the Fire & Ice Hotel in

Pretoria, The Grove Shopping Centre in

Pretoria, and the Bon Accord Police Station,

also in Pretoria.

The company also handled the piling

requirements for a new FAW auto dealer-

ship in Croydon in Ekurhuleni, as well as the

I’langa Mall in Mbombela (Nelspruit).

>