32
CONSTRUCTION WORLD
JANUARY
2015
PROJECT PROFILE
Both structures included abutments at
either end with three sets of intermediate
piers between. The south overpass was
cast as a continuous deck in three stages
along its length, whilst the north overpass
was cast in four stages split transversely into
individual spans.
Environmental impact
consideration
Where possible existing road materials were
recycled for re-use in the project. On the N9
and the N1, the base course layer was milled,
supplemented with crushed material and
stabilized with cement to form a new sub-base
layer. New pavement layer materials were
sourced from six local borrow pits and one
commercial source in Colesberg. The borrow
pits have been satisfactorily rehabilitated in
terms of environmental management plans
which were in place prior to the commence-
ment of the project.
The interchange precinct now contains
many features which enhance aesthetics and
address environmental issues. The fill and
cut slopes of the roadworks and the areas
affected by construction were rehabilitated
with the use of imported topsoil and hydros-
eeding. The seed composition was identified
by a specialist from the University of Free
State who determined the vegetation types
classification as Upper Eastern Karoo.
The site was also assessed by environ-
mental, heritage, paleontological and botan-
ical specialists prior and during construction.
Health and safety
Following the recommendations of an expert
appointed to minimise noise levels, the inter-
change precinct was further enhanced by the
construction of earth berms to reduce audial
impacts, particularly of heavy vehicles, on
residents adjacent to the roads. In addition
flood protection berms were designed and
constructed in the interchange area to control
storm water runoff, which in the recent past
had flooded the Engen access road and prop-
erty and the entrance road to Colesberg.
The project was built under trafficked
conditions and this was achieved by accom-
modating two-way traffic initially using one
way stop-go passing lanes, and later using
a two way bypass through some sacrificial
widening. This latter innovation enabled road
users to experience less inconvenience by not
having to stop and wait for oncoming traffic to
pass through the deviation.
In the case of the N1 upgrade and the
construction of the N1/N9 interchange, the N1
north and south carriageways were deviated
so that the interchange could be built without
disruption to traffic flow on the route.
The N9 and the N1/N9 interchange
precincts were maintained during the
construction period by the contractor to
ensure that the road surface was in a satisfac-
tory condition from a safety aspect while new
construction continued simultaneously.
Cost and quality
The project was completed within the
approved amended budget and the amended
time. Basil Read, in joint venture with
Newport Construction, commenced construc-
tion in March 2011 and the contract was
completed in April 2014 at a combined value
of just over R400-million for the interchange
and the N9 rehabilitation.
The N1/N9 interchange portion of the
works was delayed by three months due to
administrative issues relating to access to
the Colesberg Engen 1-Stop, which is situated
right in the heart of the planned interchange.
As a result the project was phased
so that the N9 portion of the works com-
menced as originally planned, with the N1/N9
interchange
portion
of
the
works
commencing three months later targeting and
achieving a simultaneous completion date.
This project was governed by rigid quality
control standards, which resulted in quality
acceptance testing for all road and concrete
materials. During this process more than
8 000 quality tests were carried out on the
road layers and pavement structure and more
than 7 000 quality tests were carried out on all
the concrete structures.
Risk management
Risks that were successfully managed and
overcome included the following:
The comprehensive stakeholder consul-
tation process resulted in a three month
delay in the interchange construction but was
resolved to the satisfaction of all concerned.
While the N9 rehabilitation started on
time, it was soon discovered that the roadbed
adjacent to the route was saturated due to
exceptionally high rainfall experienced in the
area. The saturated in-situ materials were
unable to drain due to impervious underlying
layers and had to be removed and replaced
with suitable rock fill from various sources
such as widened cuttings and blasting from
borrow pits. Ultimately 40 000 m
3
of rock fill,
which required urgent sourcing and procure-
ment, was placed to enable the project to
proceed. This resulted in the programme
being extended by almost six months.
Hard rock materials such as crushed stone
base course, surfacing aggregate, crusher
dust and concrete stone were to be supplied
from a separately operated source about
45 km south of Colesberg. However the
dolerite stone from this source failed the
durability requirements and the contractor
proposed an alternative in Colesberg. This
alternative source was tested and approved,
with significant cost savings due to its prox-
imity to the site. Had this alternative not been
successful, the probable resultant delays may
have had a significant negative cost impact on
the outcome of the project.
Preparing the deck formwork north overpass.
Low perspective of south overpass.
2




