CONSTRUCTION WORLD

JANUARY

2015

To accommodate the public

utilising this road and provide stra-

tegic crossings for local commu-

nity, there are 10 underpasses for

livestock and pedestrians.

The immediate purpose of this road is

to serve as an access route to the KM III

International Airport from the National

Road MR3, which runs from Manzini to

Simunye. In future this will be the main

corridor link between two borders Oshoek

and Lomahasha, and will link the Swazi

capital city of Mbabane and the Mozambican

city of Maputo.

Background

The Mbadlane Access Road to KMIII Inter-

national Airport commenced operations

in February 2011. At this time the site only

had 25 employees, however by the end of

the year the numbers had elevated to 223

employees who worked 257 730 hours with a

minimum of eight subcontractors.

The contract includes road works and

civil works, the complexity and value has

The project is called ‘D42 –

access road to King Mswati III

International Airport’.

It is a two-lane dual

carriageway which consists

of a total 18 km of asphalt

surfaced road. There are four

concrete motorway bridges

and three structural steel

pedestrian bridges across

the full span of the road.

ROADS AND BRIDGES

>

made it Inyatsi Construction’s (IC) leading

site. One of the unique aspects of the

project is the construction of a free-

flowing interchange which is the first of its

kind in Swaziland.

The project, being a multi-disciplinary

and complex one, has been in the forefront

of career development in the company.

The extensive operations and valued expe-

rience gained on this project has resulted

in the training and development of three

new junior site agents who have since been

promoted to run their own sites. A total of 38

unskilled labourers were grade tested and

hired on permanent basis and are now fully

fledged plant operators and artisans.

Design innovation

Included in the contract is the structural

design of all bridges and drainage structures

and value engineering of the project a whole.

The proposed cross sections comply

with the standards that are currently

adopted by the Ministry of Public Works

and Transport for roads of this type. This

includes the proposed new dual carriageway

from Manzini to Mbadlane, to which this

road will link.

The relatively flat grades in the original

design have resulted in fills as high as 19 m

and cuts as deep as 24 m in some sections.

The proposed 1:1.75 slopes on these cut

and fill banks may result in stainability

problems as some of the locally available

cut/borrow material has very low cohesion.

The proposed road embankment shall have

slopes of 1:2 for cut and fill.

The proposed design also takes cogni-

sance of the fact that the road traffic

volume being served is primarily made up of

passenger vehicles such as busses.

The minimum grade has generally been

increased from 0,5% to 1%. The existing link

to the airport has been constructed at 0,3%,

so the last 5 km of the access road from

the traffic circle has been designed to tie in

with this. The increased grade will improve

drainage characteristics and reduce the

likelihood of elevation offset of stormwater

drains, since these have to be on a grade of

1% to prevent silting.

Technology

Although in Swaziland the construction

industry has been built around brick,

mortar, steel and hard labour, IC recognises

the importance of technology in this field.

As a result the company has introduced new

technologies in the country.

Some of the most recent technologies

in Swaziland that are used for the Mbad-

lana Access Roadsite are the Trimble and

the recycler. The Trimble integrates a wide

range of positioning technologies including

GPS, laser, optical and inertial technologies

with application software, wireless commu-

nications and services to provide complete

commercial solutions. Its integrated solu-

tion allows employees to collect, manage

and analyse information faster and easier

making site operations more productive,

efficient and profitable. Getting the job done

right the first time (which is Inyatsi’s motto)

eliminates rework, saving the company

many costs. Through the use of these tech-

nological improvements: labour, plant,

fuel and supervisory costs are significantly

reduced. However, the greatest saving is on

material, where greater control on the levels

and quantity of materials required results in

reduced wastages. With the Trimble more

time is spent being productive and less time

waiting for surveying and levels checking.

Quality/ISO

The decision to adopt and implement the

King Mswati III International Airport