Local Fuel plc - Shoreham Oil Terminal

Safety Instrument System Functional Safety Assessment Stage 5

P & I Design Ltd

DOCUMENT NO: LF364100_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: B DATE: 07.06.2016

Tel: + 44 (0)1642 617444

PAGE 34 OF 51

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

6

CONCLUSIONS

6.1

FSA

Following this FSA, all actions have now been completed, the SIS has been fully tested and

is now within the operational phase of the SIS lifecycle. The PFD of the installed system

complies to the requirements of a SIL 2 system and management procedures have been

developed to control the SIS throughout the late lifecycle phases. It is necessary for the system

owner to ensure that the SIS provides the calculated level of protection by monitoring,

recording and analysisng all activities associated with the SIS, including activations, spurious

activations, maintenance activities, proof testing also to ensure that any proposed further

modifications are reviewed prior to the modification commencing.

6.2

System Enhancements

There are no intended system enhancements planned or needed for the SIS at this moment in

time.