Previous Page  18 / 60 Next Page
Information
Show Menu
Previous Page 18 / 60 Next Page
Page Background

16

MODERN MINING

April 2016

MINING News

Mine construction activity at Fekola builds up

Canada’s B2Gold reports that early works

were completed and activities ramped up

in preparation for full construction of its

Fekola project in Mali in the fourth quarter

of 2015. Significant activities included for-

mal ground-breaking ceremonies for the

project with local and national leaders,

clearing and topsoil removal at the tailings

basin, camp and workshop construction,

and earthworks and steel piling installa-

tion in the mill and leach tank areas.

Numerous major mill packages have

been issued for purchase including grinding

mills, crushers, tanks, and motors. Detailed

design for the Fekola plant and infrastruc-

ture construction is being completed by

Lycopodium Engineering (Australia). This is

the same engineering group that was used

to design the Otjikoto project in Namibia

and many of the same Lycopodium project

engineers are involved in the design phase.

Additionally, many of the same vendors

that have provided equipment to Otjikoto

have been successful in their bids on equip-

ment packages for the Fekola infrastructure

and plant.

The 2016 construction and develop-

ment budget for the Fekola project totals

approximately US$233 million. In 2016, the

company will continue to develop the proj-

ect with work in all major areas. Excavation

and compaction of the mill area will be

supported by an on-site geotechnical labo-

ratory and concrete will be provided by an

on-site batch plant. Structural steel and

tank erection is expected to begin in the

second quarter of 2016. Major earthworks

to be undertaken in 2016 include the tail-

ings storage facility and the surface water

dam. Based on current assumptions, the

project remains on schedule to commence

production in late 2017.

Fekola will be a substantial gold pro-

ducer with a planned average gold

production for the first seven years of

approximately 350 000 ounces per year at

an average cash operating cost of US$418

per ounce and for the life of mine plan

approximately 276 000 ounces per year at

an average cash operating cost of US$552

per ounce. The total pre-production capital

costs are estimated to be US$395 million

plus US$67 million of anticipated mine

fleet and power generator costs which are

expected to be lease financed.

Tharisa, South Africa’s only PGM and

chrome co-producer, reports it recorded a

number of milestone achievements during

the three months ended 31 March 2016 as

its mining and processing reached steady

state levels on an annualised basis.

A continued focus on safety contrib-

uted to a significant reduction in safety

related stoppages in Q2 FY2016 with a lost

time injury frequency rate as at 31 March

2016 of 0,3 per 200 000 hours.

Second quarter milestones included (on

an annualised basis) reef mined exceed-

ing the steady state required run rate of

4,8 Mt/a, mill throughput at nameplate

design capacity and contained PGM pro-

duction on a 6E basis meeting the steady

state production level.

“We are very encouraged by the mile-

stones achieved during this, our second

quarter. Not only have we achieved

improved production, we have exceeded

Tharisa achieves steady-state production levels

previous records,” says Tharisa CEO

Phoevos Pouroulis.

Tharisa’s mining operations are charac-

terised by the shallow open-pit, large scale

co-production of PGMs and chrome con-

centrates with a consequential low cost of

production.

Improvements in reef mined during the

quarter resulted from a continued focus on

opening up access to the full mining strike

length and the benefits of maintaining

Night view of the Tharisa mine, which is located on the south-western limb of the Bushveld Complex, near Marikana (photo: Tharisa).