Previous Page  37 / 60 Next Page
Information
Show Menu
Previous Page 37 / 60 Next Page
Page Background

GOLD

April 2016

MODERN MINING

35

Houndé

Above:

Layout of the

Houndé mine.

Left:

Drilling at the Houndé

site in Burkina Faso.

Ownership

90 % Endeavour, 10 % Burkina Faso

Reserve and Resources

P+P Reserves

31 Mt at 2,1 g/t Au for 2,1 Moz

M+I Resources (inclusive of reserves) 38 Mt at 2,1 g/t Au for 2,5 Moz

Inferred Resources

3 Mt at 2,6 g/t Au for 0,3 Moz

Mine type

Open pit

Mill type

Gravity/CIL plant

Production

Mine life

10 years

Strip ratio, W:O

8,4

Processing rate

3,0 Mt/a

Average LOM Recovery rate

93 %

Total LOM gold production

1 906 koz

Average annual production

190 koz

Average LOM AISC

US$709/oz

Houndé Project Highlights

offset the power costs increasing from US$0,15

to US$0,18 per kWh.

Site General and Administrative (G&A) costs

have decreased due to favorable exchange rate

variations and re-allocation of fixed labour

costs into mining costs.

The optimised and fully scoped upfront cap-

ital cost has been estimated at US$328 million,

inclusive of US$47 million for the owner-min-

ing fleet and US$28 million for contingencies,

which is in line with the 2015 estimate of

US$32 million.

The current upfront capital cost estimate

is based on power supply from Sonabel, the

national electricity utility, consisting of a

38 km, 91 kV overhead power line.

Project capital commitment in 2016 is

expected to be approximately US$180 mil-

lion, with the remainder in 2017. Within the

coming weeks, Endeavour expects to lock-in

approximately 25 % of the total capital cost by

placing firm orders for the SAG and ball mills,

purchasing the mining fleet and paying land

compensation and related taxes.

Replicating its successful construction

partnership at other mines it has developed,

Endeavour has awarded the EPCM contract

to Lycopodium Minerals, and detailed engi-

neering is now commencing. Lycopodium

has already had detailed involvement in the

Houndé project, through the completion of

the Detailed Feasibility Study and the recently

completed optimisation reviews.

The overall duration of the project construc-

tion is estimated to be 18 months – with the

first gold pour expected in the fourth quarter of