Previous Page  32 / 60 Next Page
Information
Show Menu
Previous Page 32 / 60 Next Page
Page Background

GOLD

30

MODERN MINING

April 2016

A

ccording to African Gold Group,

Inc, which is listed on the

TSX‑V, the FS demonstrates

the robust nature of the project,

with the highlights including an

‘All In Sustaining Cost’ (AISC) of US$788 per

ounce and free cash flow of US$122 million

net of all capital expenditure, operating costs,

royalties and taxation in Mali, at a gold price

of US$1 200 per ounce. Mining and processing

supports gold production exceeding 50 000

ounces per annum over an eight-year mine life.

The low capital and operating costs of the

project reflect the fact that the deposit is eas-

ily mined and that the process plant will be

a relatively simple modular facility with only

modest milling requirements. The total power

requirements for the project are estimated at

just 1,9 MW, to be supplied by diesel gensets.

Located 125 km south-west of Mali’s capital,

Bamako, Kobada – acquired by African Gold

in 2005 from French company Cominor – has

its permitting in place, with the environmental

permit having been granted in June last year

and the mining licence shortly thereafter in

July. A community development plan (essen-

tial in Mali’s permitting process) has also been

completed.

The total measured and indicated mineral

resource at Kobada contains 1,21 Moz of gold,

with a further 1,02 Moz in the inferred category.

The FS only considers the processing of oxide

ore types. The proved and probable mineral

reserve is estimated to be 12,7 Mt at 1,25 g/t

containing 511 000 ounces of gold. The reserve

was reported within the optimised pit design

and above a cutoff grade of 0,53 g/t Au.

While the mineral reserve comprised only

material from the M&I resource, there remains

Mali’s Kobada open-pit gold

African Gold’s pilot plant at the Kobada site. It has a

throughput capacity of up to 2 t/h and is specifically

designed for metallurgical research.

Mali has a host of gold projects currently at various stages

of development, including B2Gold’s Fekola project, already

under construction and destined to be a plus 300 000 ounce

a year producer, Hummingbird’s Yanfolila and Avnel Gold’s

Kalana. Perhaps less well publicised than these is African

Gold Group, Inc’s Kobada gold project. Compared to Fekola,

it will be a relatively small mine but the recently completed

Feasibility Study (FS) demonstrates that it has attractive

economics, with the payback period on the estimated pre-

production capex of US$45,4 million being 31 months.

an important opportunity to improve the

resource category of the large inferred mineral

resource immediately to the north and south of

the reserve pits. African Gold plans to fund the

development of this resource upgrade from the

internal cash flow of a producing mine.

Contract mining is planned to be undertaken

using 40-t dump trucks and 70-t excavators.

This type of equipment is relatively common

in Mali, which allows significant flexibility in

scheduling the mining programme. The min-

ing schedule aims to deliver 1,6 Mt/a of ore for

processing. The saprolite to be mined is free

digging although it is anticipated that minor

use of blasting might be required for some parts

of the overlying laterite cap.

The life of mine strip ratio is estimated to be

3,28 to 1 (waste tonnes to ore tonnes). The strip

ratio during the first two years is maintained

at less than 2 to 1 with the mining of starter

pits. The final cut back is then initiated, with

the mining rate increasing to 11 Mt/a.

Further metallurgical test work was com-

pleted as part of the FS. A 305 kg sample of

saprolite ore was obtained from 64 m below

surface to examine the metallurgical response