Previous Page  27 / 60 Next Page
Information
Show Menu
Previous Page 27 / 60 Next Page
Page Background

April 2016

MODERN MINING

25

COVER STORY

months in 2014 while Ivanplats awaited the

formal execution of its 30-year mining right.

Since then it has been all systems go with the

main focus of activity being the 7,25 m inter-

nal diameter, 975 m deep, concrete-lined No 1

shaft, one of the cornerstones of phase one.

When

Modern Mining

was on site recently, the

pre-sink had been completed to 54 m and the

shaft-sinking contractor, Aveng Mining Shafts &

Underground, was preparing for the slow sink

stage (the preliminary to the main sink) with

the 40 m high steel sinking headgear erected,

the five-deck stage in position in the shaft and

the final installation of the double-drum kibble

winder and four-drum stage winder underway.

According to Mouton, the shaft-sinking will

employ tried and tested traditional methods

using conventional jumbo drill rigs and cactus

grabs. “We would expect Aveng to achieve an

advance rate of 2,5 m a day once in full sink

mode and at this stage we are anticipating inter-

secting the Flatreef at a depth of 777 m in late

2017 with shaft bottom being reached in 2018,”

he says. “Although Shaft 1 is designated as the

primary ventilation intake shaft, we will be

hoisting through it as it will be used for early

underground development and this hoisting

role might become permanent as we move into

phase two.” He adds that development work

will include three stations at depths of 450 m,

750 m and 850 m below surface.

Shaft 1 is the smaller of the two main shafts

required for the full implementation of the

phase one Platreef project. The main pro-

duction shaft will be Shaft 2, which – once

completed – will rank as one of the biggest

shafts in the platinum mining field in South

Africa. Located just 100 m from Shaft 1, it will

have an internal diameter of 10 m and be sunk

to a depth of 1 250 m below surface. Capable of

hoisting 6 Mt/a, it will be equipped with two

high-speed 40-tonne skips running at 18 m/s

and will also be capable of conveying 225

persons in a single deck using a cage and coun-

ter-weight arrangement. At this stage, Ivanplats

is expecting to start early works for Shaft 2 in

2017, including civils work for the boxcut and

hitch foundation.

The headgear of Shaft 2 will be an impos-

ing concrete structure, 100,5 m high, making

it similar in size to the concrete headframe

of Impala’s No 16 shaft near Rustenburg. It

will accommodate two Koepe winding sys-

tems which will be positioned 82 m above

ground and – at a lower elevation – a single

drum auxiliary winder. The contract for the

design of the headframe – now complete – was

awarded to Murray & Roberts Cementation in

2014. Interestingly, the company has produced

a 1:260 scale model of the headgear using 3D

printing technology (see our photo), represent-

ing its first use of this technology. The model

was printed using ceramics as opposed to plas-

tics for aesthetic purposes, with the printing

process taking just 17 hours.

One of the reasons for the generous dimen-

sions of Shaft 2 is the fact that it will be used

to transport large trackless equipment under-

ground. Explains Mouton: “Based on the

recommendations of the PFS, we’ll be using

highly mechanised mining methods requiring

the use of some very large mining equipment

– for example, 40 and 50-tonne capacity min-

ing trucks and 14 and 17-tonne LHDs. These

machines will ‘live’ underground where we

will have workshops initially but, of course, we

have to get them down there in the first place

and also occasionally bring them to surface for

complete rebuilds. The dimensions of Shaft 2

will allow us to do this, although the bigger

machines will still have to be broken down to

allow them to fit within the cage.”

Transverse longhole stoping on a retreat

basis will the mining method applied to ore

zones with vertical thicknesses greater than or

equal to 18 m while thinner ore zones will be

mined using mechanised drift-and-fill or drift-

and-bench methods. Paste backfill will be used

for post-mining support although in the first

two years of production (prior to the startup of

the mill and the paste backfill plant) cemented

rock fill will be used as the fill system. Most of

the cemented paste fill (CPF) preparation sys-

tem will be located on surface with the only

underground components being the pipeline

distribution to the stopes.

Commenting on the use of longhole stop-

ing, Mouton says that the method – which is

The stage and bank steel be-

ing lowered into Shaft 1.

“Although Shaft 1

is designated

as the primary

ventilation intake

shaft, we will be

hoisting through

it as it will be

used for early

underground

development and

this hoisting role

might become

permanent as we

move into

phase two.”