April 2016
MODERN MINING
23
COVER STORY
Reducing the impact of the Platreef mine
One of the challenges of the Platreef project is that it occupies a relatively
compact site in close proximity to a number of villages and informal settle-
ments. Ivanplats’ engineers are therefore making every effort to ameliorate
the dust, noise and visual impacts of the project and to ensure the safety of
community members.
All construction activities are taking place within a 345 ha fenced con-
struction compound and a 10 m high berm will be built which will help
reduce noise levels and also reduce the visual impact. Non-mineralised rock
from the shaft and underground development workings will be used to cre-
ate the berms, which will eventually be clad with top soil and hydro-seeded.
The shaft headframes, of course, will be visible over a long distance, par-
ticularly the 100 m-high structure of Shaft 2. To lessen the profile of the
taller headframe, Murray & Roberts Cementation has incorporated unob-
trusive lighting and also implemented design initiatives to reduce noise
and dust levels. The overall aesthetics have also been considered, with the
headframe having pleasing fluted features using concrete throughout.
The tailings storage facility will be located 8 km away from the mine site –
and across the N11 road linkingMokopane with theMartin’s Drift border post
on the Botswana border – in an area where there are no communities. Ac-
cording to the design, 60 % of the total tailings will be used for underground
backfill which will reduce the overall environmental impact on surface.
The four-drum stage winder
required for the sinking
phase.
plus 500-page document – on the project in
January last year, which outlined the staged
approach to development. According to the PFS,
phase 1 will have an average annual production
rate of 433 000 ounces of platinum, palladium,
rhodium and gold (3PE+Au), plus 19 million
pounds (8 618 tonnes) of nickel and 12 million
pounds (5 433 tonnes) of copper. The PFS esti-
mates the pre-production capital requirement
of phase one at US$1,2 billion (at a Rand/US
dollar exchange rate of 11 to 1). It said the new
mine would have a cash cost of US$322 per
ounce of 3PE+Au, net of by-products, placing
it near the bottom of the cash curve. It estimates
the after-tax NPV (at an 8 % discount rate) at
US$972 million and the after-tax IRR at 13 %.
Following on from the PFS, Ivanplats is
now busy with a full Feasibility Study (FS),
which is expected to be completed in Q1 next
year, using the same team of professionals
responsible for the PFS (and for the earlier
Preliminary Economic Assessment or PEA).
They are DRA Global (process and infra-
structure), Stantec Consulting International
(mineral reserve estimation and mine plan),
SRK Consulting (geotechnical), AMEC Foster
Wheeler (mineral resource estimation), Golder
Associates (hydrology, backfill and tailings)
and Digby Wells (environmental). DRA is man-
aging the study while OreWin of Australia is
responsible for overall NI43-101 report prepa-
ration and economic analysis.
“Our strategy has been to retain the same
team throughout all the study phases as this
makes for continuity,” comments Mouton. “We
have also, of course, gone for consultants with
excellent track records. DRA, for example, has
real in-depth mining and processing expertise
and is particularly experienced in the PGM sec-
tor, where it has been responsible for designing
and building close on 50 processing plants.
Similarly, Stantec – we’re working with its
Phoenix, Arizona office – has an international
reputation in mining consulting – and indeed
in other areas of engineering – and has worked
very successfully with Ivanhoe on previous
projects such as Oyu Tolgoi in Mongolia.”
The phase one project as delineated in the
PFS is now well into construction. In fact, pre-
liminary works on site started as early as late
2013 although work was halted for several




