Previous Page  29 / 60 Next Page
Information
Show Menu
Previous Page 29 / 60 Next Page
Page Background

April 2016

MODERN MINING

27

COVER STORY

particularly suitable for thick orebodies – is

well-established globally although relatively

uncommon in South Africa where narrow reefs

predominate (although it has been used in

some gold mines). “We’re absolutely confident

that it is the right method for the Flatreef and

that it will deliver the required tonnages, at low

cost and in safe conditions,” he says.

Mouton adds that the high degree of mecha-

nisation will mean that the Platreef mine will

be an ultra-safe mine. “Mechanised methods

are inherently safer than manual methods, par-

ticularly if the operators are well trained, as

ours will be,” he maintains. “In fact, our vision

is that our operators – who will be predomi-

nantly drawn from local communities – will

be multi-skilled, well-paid professionals, who

will work in air conditioned cabs in well ven-

tilated spaces. To enhance safety even further,

the mine design is such that it will minimise

all man-machine interfaces. Ivanhoe’s manage-

ment has stressed that the goal is to make the

new mine one of the safest in the world and

this objective has been prioritised in all our

planning, design and engineering.”

Despite the level of mechanisation and the

elimination of labour-intensive procedures, the

Platreef mine will be a substantial employer

even in phase one, with the projected work-

force within four years of the start of operations

expected to be in the vicinity of 2 200 people.

Says Mouton: “We are committed to employ-

ing at least 70 % of our workers locally. This

will require that we invest very heavily in

training and this process has already started

as part of our Social and Labour Plan commit-

ments. In conjunction with the Department of

Labour, we have created a database which will

be used to select candidates for training and

already we have 23 000 names on it. We’ve

also committed to building a community skills

and development and training facility in the

Mokopane area within five years – a project

which will cost around R26 million.”

Of course, building a mine the size of the

Platreef operation in an area where water

supplies are limited and in a country where

electricity supply is constrained brings with it

its own set of challenges on top of those pre-

sented by the task of creating a cutting-edge

underground mine. The mine will need up to

100 MVA of power (for the 4 Mt/a production

level) and also consume up to 10 million litres

of water per day.

“As regards to power, we have enough genset

capacity on site for the shaft sinking and we

will be receiving a permanent 5 MVA supply

from Eskom for the construction phase,” says

Mouton. “Work on the

internal electricity sub-

station for this has been

completed and construc-

tion of the powerline is in

progress. Longer-term we

are confident of getting

the electricity we need as

our startup will occur just

as the new Medupi Power

Station is reaching its full

capacity. We have already

agreed a 70 MVA bulk

supply with Eskom and

are in discussions regard-

ing the further 30 MVA

that may be required.

“With respect to water,

we will be drawing from

the Olifants River Water

Resources Development

Project, which includes

the raised Flag Boshielo

Dam and the Phase 2B

pipeline. We are also

investigating other bulk

water resources so that

we have a back-up plan

in the event that delivery

of water from the Olifants

project is delayed.”

He adds that the mine – as one would expect

– will incorporate modern technologies to

save on energy and that it will also be an eco-

nomic consumer of water, with extensive use

of recycling.

Summing up the project, Mouton says that

the construction underway at presents repre-

sents the culmination of nearly two decades

of work by Ivanhoe, which started explora-

tion work at the Platreef site in the late 1990s.

“We are pleased with the current progress on

site and are on course to produce our first con-

centrates in 2019. We also believe we have the

overwhelming support of the local communi-

ties who are excited by the employment and

business opportunities the new mine presents.

We are very aware of the need to have a social

licence to mine and the MD of Ivanplats, Dr

Patricia Makhesha, and rest of the Ivanplats

team are working ceaselessly to ensure that

the mine meets – and exceeds – the require-

ments of the Mining Charter. Overall, this is a

transformative project with the capacity, on one

level, to revolutionise platinum mining and, on

another, to benefit a huge range of stakeholders

within the Mokopane area.”

Report by Arthur Tassell, photos courtesy of Ivanplats

Model of Shaft 2 created

by Murray & Roberts

Cementation using 3D

printing technology.