Physical reverse flow from NI to GB and IE via SNIP pipeline
General Information
Promoter
Premier Transmission
Limited
Operator
Premier Transmission Ltd
Host Country
United Kingdom
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
Premier Transmission Ltd
100%
TRA-N-027
Project
Pipeline including CS
Non-FID
Update Date
22/06/2016
Non-Advanced
Description
Installation of bi-drectional compression on Scotland to Northern Ireland pipeline (SNIP); pipework modifications at 2 AGI's to allow bidirectional
metering and flow control and moving gas odourisation point to a new point(s) downstream of the bidirectional transmission system.
Regulatory Decisions and
similar material conditions
Enabled Projects
Project Code Project Name
UGS-N-294 Islandmagee Gas Storage Facility
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Twynholm
Premier Transmission Ltd
2021
UKn/PTL
Y-UKm
131.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 551 of 620
Current TYNDP : TYNDP 2017 - Annex A