Physical reverse flow from NI to GB and IE via SNIP pipeline

General Information

Promoter

Premier Transmission

Limited

Operator

Premier Transmission Ltd

Host Country

United Kingdom

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

Premier Transmission Ltd

100%

TRA-N-027

Project

Pipeline including CS

Non-FID

Update Date

22/06/2016

Non-Advanced

Description

Installation of bi-drectional compression on Scotland to Northern Ireland pipeline (SNIP); pipework modifications at 2 AGI's to allow bidirectional

metering and flow control and moving gas odourisation point to a new point(s) downstream of the bidirectional transmission system.

Regulatory Decisions and

similar material conditions

Enabled Projects

Project Code Project Name

UGS-N-294 Islandmagee Gas Storage Facility

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Twynholm

Premier Transmission Ltd

2021

UKn/PTL

Y-UKm

131.0 GWh/d

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 551 of 620

Current TYNDP : TYNDP 2017 - Annex A