Technical Information (UGS)

Storage Facility

Islandmagee Storage

Facility

Storage Facility Type

Salt Cavern

Multiple-Cycle

Yes

Working Volume (mcm)

420.00

Time Schedule

Grant Obtention Date

Delay Since Last TYNDP

approx 3 years

Delay Explanation

The project has been delayed due to absence of competitive tariffs for gas storage.

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project aims at fulfilling the infrastructure standard (N-1) rule at regional level in accordance with

Article 6(3) of Regulation EU, Project concerns investment in reverse flow capacity, Project aims at supplying directly or indirectly at least two

Member States

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

The Islandmagee facility will enhance physical and price security of supply for the Northern Ireland, Republic of Ireland and Great Britain gas

markets.

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

2021

2026

NDP and PCI Information

Part of NDP

Yes (Northern Ireland Gas Capacity

Statement)

NDP Number

n.a.

Currently PCI

Yes (5.1.3)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Not Applicable

Considered Tariff Regime

Not Applicable

Applied for Exemption

Not Relevant

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%