Page Background

Industrial Emisssion Directive (IPPC) - Non-FID

General Information

Promoter

National Grid Gas plc

Operator

National Grid Gas plc

Host Country

United Kingdom

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

TRA-N-349

Project

Pipeline including CS

Non-FID

Update Date

25/05/2016

Non-Advanced

Description

Emissions related investment, which aims at replacing non-compliant gas compressors with electric drives.

Regulatory Decisions and

similar material conditions

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

Unknown

Unknown

NDP and PCI Information

Part of NDP

Yes (Gas Ten Year Statement 2015)

NDP Number

Section 5.2

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

Not Relevant

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%