Industrial Emisssion Directive (IPPC) - Non-FID
General Information
Promoter
National Grid Gas plc
Operator
National Grid Gas plc
Host Country
United Kingdom
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
TRA-N-349
Project
Pipeline including CS
Non-FID
Update Date
25/05/2016
Non-Advanced
Description
Emissions related investment, which aims at replacing non-compliant gas compressors with electric drives.
Regulatory Decisions and
similar material conditions
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
Unknown
Unknown
NDP and PCI Information
Part of NDP
Yes (Gas Ten Year Statement 2015)
NDP Number
Section 5.2
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
Not Relevant
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%