Expected Gas Sourcing
LNG (WO)
Benefits
Main Driver
Market Demand
Main Driver Explanation
We consider that a growing amoun of flexibles volume will be available. These volume will allow more competitiveness in the south region but will
required more regas capacity as well as a strong logisitcal support (jetty + tank) to allow the shipper to take advantage of spot market opportunity by
buying/unloading and reselling/reloading according to the stronger price signal of the Mibgas. This project will be neccesary if an increase demand or
export scenario will occur.
Benefit Description
Mugardos terminal is ideally located to take advantage of the US FOB volumes.
Technical Information (LNG)
LNG Facility
Mugardos LNG Terminal
Expected Volume (bcm/y)
4
Storage Capacity (m3)
0
Ship Size (m3)
0
Reloading Ability
Yes
Schedule
Start Date
End Date
Pre-Feasibility
06/2010
Feasibility
06/2010
11/2010
FEED
04/2021
10/2021
Market Test
10/2021
Permitting
09/2021
03/2022
Supply Contracts
06/2022
FID
06/2022
Construction
06/2022
12/2023
Commissioning
2023
2025
NDP and PCI Information
Part of NDP
Yes (PLANIFICACION ELECTRICIDAD Y
GAS 2008-2016)
NDP Number
N/A
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM